80% works to link Chilime hydel to central feeder complete Nuwakot,
March 21 (RSS): It
is a 39-kilometre distance between the 20-megawatt capacity Chilime Power House to the
Trishuli and Devighat Hydroelectricity Centre and 92 of the 125 electricity pylons
required to cover the distance have been constructed, chief of the Chilime Power Project
Mr. Bishnu Prasad Upadhyaya told RSS. He
said power transmission lines have also been installed along the distance. The entire work
is expected to be completed by July end. The
towers have been constructed at a distance ranging from 175 metres to 1240 metres
depending on the relief features of the terrain, he said. The construction works for the 66-kv
Chilime-Trishuli-Devighat transmission had begun in January 1999 with the joint investment
of about Rs 20 million from His Majestys Government and Nepal Electricity Authority. Other Story |
|Headline| |Editorial| |Features| |Local| |Sports| |Letter| |Past| |Home|
| Send your comments and letters to the
editor at gopa@mos.com.np 1999 © Mercantile Communications Pvt. Ltd. P.O. Box 876, Durbar Marg, Kathmandu, NEPAL. Tel : 977 1 220 773, 243566, Fax: 977 1 225 407. Reproduction in any form is prohibited without prior permission. No part of the articles which appear in the internet version on THE RISING NEPAL may be reproduced without the permission of Mercantile Communications Pvt. Ltd. For reprinting rights, please write to us. Send us your feedback: contact us. |