http://www.nepalnews.com

October, 2002

Sectoral

Development Bank’s Demands

Now that the commercial banks, the finance companies and the cooperative finance companies are already made to follow the prudential banking norms, Nepal Rastra Bank is reported to be finalising almost similar directives for the development banks as well. And the development banks fear that the proposed directives are going to be unjustifiably harsh for them.

“Almost 80% of the provisions in the proposed directives are the same as those issued for the commercial banks and finance companies. That is not justifiable for development banks”, says Sudhir Khatri, President of Development Credit Bank Ltd. (DCBL), one of the participants in a recent discussion organised by the central bank on the proposed directives to the development banks.

Though the development banks have forwarded their suggestions to the proposed norms, they fear that the central bank is not likely to listen to their pleas because they are not as strong as the commercial banks to lobby effectively with the NRB and to make it stoop to their demands.

One of the complaints that the development banks are making is about the restriction NRB is going to put on the promoters of the development banks on selling their shares. According to the initial rule as per the Development Bank Act, the promoters were allowed to sell their shares after two years of the beginning of operation of the development bank. That was later extended to three years, and now it is being extended further to five years. “Such an attempt to block the capital of the promoters is like a blackmail”, says Khatri. “If there are cases of some promoters of some development banks misusing the provision, NRB should be able to take action against them by improving its monitoring capability, but it cannot penalise all the promoters of all the banks.”

Moreover, the forthcoming rule is also to have a provision that restricts the promoters from taking loan from the development bank they have promoted. This, coupled with the provision against the sale of the shares, is too harsh, says Khatri, and demands that the central bank should permit some way out for the existing shareholders in the development banks to sell their promoters’ stake so that they can continue with their normal businesses.

According to Khatri, the forthcoming rule is also to allow the development banks to accept saving deposits as was being demanded by them, but the permission is coming with a catch. It requires the development banks to park 1% of their total deposits with NRB in an interest-free account. Though the Cash Reserve Ratio (CRR) for development bank is being reduced to 8% from the earlier 10% to make it easier for them, it is not going to actually benefit the development banks because the CRR has been reduced also for the commercial banks, thus keeping the relative difference in the cost of funds of the two the same.

Though the commercial banks and development banks were conceived initially as different categories involving into different types of businesses, thus reserving some of the businesses for the development banks, that difference is being reduced, putting the terms now more against the development banks, complains Khatri. For example, the Development Bank Act allows a development bank to go into venture capital financing, and as Khatri says, his bank has already made such financing in some of the cases. But the forthcoming rule is to restrict such financing only on companies that are already listed on the stock exchange or are likely to be listed within the coming year. Similarly, housing was a sector where only the development bank was allowed as per the Development Bank Act, but now NRB has permitted commercial banks too to go into this sector, from where the development banks are likely to be driven out because they can not compete with commercial banks due to the difference in the cost of funds.

One demand that the development banks have been repeating all along is the permission to operate the current account which will help them to reduce the cost of their fund. Though the central bank is not willing to grant them this right as this will make the development banks able to create credit money (a function which by definition should be restricted to commercial bank only), the development banks say, they need to operate current account for their clients if not for the general public. “We need it for two reasons”, says Khatri. “One, if we have the current account of our client with us, the record of the transaction in that account helps us to monitor the business of our client and take necessary action in time if there are early warning signals. Second, if we send our client to the other commercial banks with our cheque, there are high chances that our good clients will be snatched away from us by the commercial banks.”

Also regarding the proposed capital adequacy ratio (CAR), the development banks say the central bank is not doing justice to them. “We are being asked to maintain 10% CAR right from the beginning, while the commercial banks had the comfort of gradually increasing it to the present level, for example from 9% in the last year. Now they say that the central bank will consult the CBs before raising it further. But in our case it is going to be increased right away”

“What we are concerned still more is about the rule that is being proposed for loan loss provisions”, says Khatri. The central bank is proposing to have a system of provisioning that is equal to that applied to the commercial banks. Khatri points out that since provisioning is to be made only in case of term loans and the commercial banks have only about 20% of their portfolio as term loans, they are not much affected by the rates for provisioning. But in case of development banks, almost all of their portfolio (70-80%) is made of term loans, thus the cost of provisioning is very high for the development banks.

The result of all these strict arrangements is going to be still higher cost of funds for the development banks. Moreover, since the areas that were previously reserved for the development banks are now opened also for the commercial banks, Khatri moans that the development banks will not be able to face the competition. “And it is not fair, because this means the withdrawal of all the facilities that were promised in the beginning to the promoters of the development bank.”

Pointing out the practice abroad, Khatri notes that in India the Industrial Credit and Investment Corporation of India Ltd. (ICICI) has its own commercial bank –ICICI Bank – to cater to the needs of its clients and this makes it able to compete with the other commercial banks.

Against this background, solution here would be to speed up the introduction of the Universal Banking Act, which is still being drafted. Till then, the controversy is likely to linger. With such an Act, any banking institution may upgrade itself to any other category by fulfilling certain conditions after which they can enjoy certain specified privileges. Similarly, they can also be demoted to lower category for failing to fulfil the requirements for the current category.


The ABC Controversy

by Krishan Prasad Sigdyal

An account of the plight of Nepali entrepreneurs deprived of the opportunity to participate in the tender process for jobs under development projects funded by donor agencies.

The controversy concerning the ABC (Aerial Bundled Cable) supply to the US$ 50 million Asian Development Bank (ADB) funded 8th Power Project (OPEC and HMG fund has also been mobilized for it), presents a fascinating case to study the developmental issues facing Nepal.

The tender document for various packages for supply of goods and services is to be released for publication soon (one is already out). The media in the country has brought to light some of the issues related to it.

The packages include supply on the turnkey basis of some of the sub-stations, and transmission equipment such as concrete poles, tubular (metallic) poles, transformer, hardware (pole accessories), Aluminium Conductor Steel Reinforced (ACSR) conductor, ABC and concentric cable for distribution from the poles to the consumer’s (consumption measuring) meter-box. The sub-stations are considered beyond the reach of the Nepalis because it involves some equipment including high power transformers not ‘known’ to them, although it is sure to be executed almost on a turn-key basis on sub-contract once it is awarded to the ‘foreign’ principal.

The concrete poles were broken, it is reported, into several packages to allow Nepali industries to participate in the bid presumably because it is a low value material. High value and ‘high-yield’ packages have been reserved to foreigners through a web of financial and mainly technical clauses (so much so even the internationally acceptable practice of dividing cables in broad low and high voltage category has been further divided into specific names) basically to keep the Nepalis out from participation. The ABC package is out of the reach of the Nepalis on the pretext that they have no experience in it. The officials refuse even to discuss the case of ABC package.

Even different materials such as the ACSR Conductor and the Concentric Cable have been lumped together. It forms a package of about US$ 7 million. God, or the concerned officials only, (the top officials of NEA including the managing director have been changed recently) would know why they were not split into small packages like the concrete or metallic poles.

There are about a dozen cable and conductor industries in Nepal. Many of them have been there for over two decades fulfilling all kinds of NEA and power project need of cable and conductors of low and high voltage-be it for Kali-Gandaki ‘A’ or to Chilime. However, the cable and conductor factories were initially deemed unfit for supplying to Distribution System Reinforcement Project, one of the six project components of the Rural Electrification, Distribution and Transmission project (so-called 8th power project).

Finally, when the cable and conductor factories represented their case vigorously, and the media took the matter up, the officials began to realize their weaknesses. The financial criterion was such that no Nepali company, even 10 years hereafter, would be able to qualify for bidding under the original condition. For example, under the initial draft, a bidding company should have supplied the goods continuously for three consecutive years and three times equal the quantity to be supplied under the bid’s one year supply package. However, this has been modified now, they say, to enable the indigenous industries to compete in a joint-venture bid for the ACSR and Concentric Cable Package.

The project officials saw the need to take it up with the ADB counterparts only after the Nepali manufacturers made a hue and cry about it. They did not feel the need to look at the ‘overbearing’ conditions beforehand. It is very common for all countries to negotiate the terms and conditions with donors to stimulate the growth of national economy – this does not seem to be the case with the 8th Power Project despite the fact that far-reaching decisions were made to effect the US$ 50 million loan. Besides, it will not help NEA to increase its rate of return (ROR) and self-financing ratio (SRF), because generally products manufactured in Nepal have been found to be cost effective in NEA’s own experience.

Furthermore, the issue of Nepali companies to bid jointly for the ABC package (US$ 7 million) is still in a limbo. The ABC, although a low-voltage insulated cable falling very well within any low-voltage insulated cable category by any national or international standard in the world, is deemed outside the ‘capacity’ of Nepali industries because they have no supply record to NEA, or any other buyer of the particular cable! Nepali insulated cable manufacturers have been manufacturing more than 200 kinds of insulated cable in the low-voltage category, and bare conductors in the high voltage category as well.

This brings us to the centre of the perpetual and self-inflicted vicious circle rendering Nepal to assume the title of ‘permanently disabled’ least developed country.

The case herefrom would be more interesting even for those unaware of the Nepali scenario. It would be hard for development scientists and economists to find a parallel elsewhere. Nepalis, finally, seem to have lost the aptitude to rule and regulate their own affair. No surprise then that every other day someone, more recently the British Government Organized ‘London Meet’, while pledging support to combat terrorism, points out to ‘address the underlying issues of corruption, discrimination and weak governance’. Although supposedly more and more exposure has enhanced individual knowledge and capacity, institutionally it has gone ‘down to zero’.

Despite the rhetoric that appears in the national dailies on their front-pages everyday in the form of pious sermons from the so-called leaders, they are practically ‘illiterate’ to even broad development issues, least on the issues of sectoral development, regional developmental competition or the policies of the ever-engrossing dominant southern neighbour.

Under the circumstances, the bureaucrats are provided with a golden opportuniry to enrich themselves at the cost of everything that one can contemplate of. The bureaucrats inclusive of the technocrats act obediently when it comes to negotiation with a donor, and accept all condescension imposed as a stricture passed from heaven! This disposition has done a lot of damage especially in dealing with the southern neighbour on various bilateral issues.

The educated and the white-collar technocrats, in the eyes of the commoners, are self-serving ‘demons’ out there ‘to loot the country’ in the name of the poor people.

Let us go back to the 8th Power Project again. It has been in discussion for the last three or four years in public forums also. It has been the cause for 2 or 3 steep rises in NEA tariffs within a short span of time. The ADB finally signed the agreement with the government to extend the loan only after the rises were effected.

Although there seems to be some justification for HMG/NEA to accept the loan from ADB because of the apparent reforms aimed at NEA through other loan package objectives, one really would do well to give a last glance to the whole gamut once again looking at the Distribution System Reinforcement Project material procurement packages’ conditionalities. Should not the procurement packages be looked as instruments for boosting the ailing national economy, and even to justifying the increase in tariffs?

It is all right for the ADB to set general conditions suiting all 59-member countries, but is it not our responsibility to suit it to our condition? Can we, our bureaucrats and technocrats alike, shirk their responsibility from it? When the Nepali manufacturers are deliberately kept out (there are strong reasons to conclude so!), whose interests are they serving?

The project officials are not even interested to listen to the representation of the indigenous manufacturers in the case of ADB package, and point out to ADB conditions as if they were Ten Commandments of the Bible. The new top management of NEA should look into it immediately; if the conditions are so ‘holy’ and unchangeable, it should have the courage to change the ABC into Conductor, or cancel the package altogether.

The discussion also brings us to a point wherein the NEA, after completion of the ‘objectives’ of the 8th Power Project, look into the issue or raising funds from within the country to finance its development projects. The author strongly feels that it can do so after a careful homework. Are there conscientious people in the country, or even the ADB, to look into the issues raised above?

The discussion finally boils down to the need of codification in the laws of the country for an organized system of public hearing in each sector before such loans/grants are accepted by the government or else the officials shall feel free to accept any condition, and to fill in their coffers in the form of foreign bank accounts at the cost of the national economy, morale and pride! Is not the message of the ‘London Meet’ loud enough to do so?

(Sigdyal is a senior Journalist turned ‘Consultant’ in the industrial sector)


Cover StoryEditorial | Business News | Biztoon | Economy & Policy | No Laughing Matters
Personality
| Management |
Rural | Book Review | Political | World Trends | Follow-up | SectoralCorporate
  Interview | Stock Taking | Last Word | | Main | Past

Send your feedback to the editor: bizline@mos.com.np  
2002 © Mercantile Communications Pvt. Ltd. P.O. Box 876, Durbar Marg, Kathmandu, NEPAL. Tel : 977 1 220 773, 243 566 . Fax: 977 1 225 407. Reproduction in any form is prohibited without prior permission. No part of the articles which appear in the internet version on NEW BUSINESS AGE may be reproduced without the permission of Mercantile Communications Pvt. Ltd. For reprinting rights, please write to us.  Send us your feedback : contact us.

Back to the top