![]() |
|||
|
|||
KALI GANDAKI
"A" |
Bogged In
Controversies The
already delayed hydropower project may still need more time --and money -- thanks to the
disputes surrounding it By A
CORRESPONDENT State owned
projects are always taken for a ride. Whether it is the private sector or even the
official mechanism, or, in some cases, both the parties hand in gloves, perhaps none has
the record of having completed any government project without getting into controversy. The 144 MW Kali Gandaki "A" Hydropower Project of the Nepal
Electricity Authority has been no exception. Right from the time it began on January,
1997, the biggest ever hydel project has frequently been in the news for one or the other
reason. Many a time, labors' strikes in the project site in western Nepal have hit
news headlines. Cases related to irregularities and corruption on issues like procuring
construction materials, among others, have been time and again trickling in.
And now, a severe jolt has rocked the biggest ever hydropower project whose
construction cost may go much higher than what was estimated initially. Almost all the
Nepalese technical staff and two non-technical staff resigned from their positions in the
project last week.
With its 56 technicians having tendered resignation en masse, the hydropower
project runs the risk to remain incomplete even after its renewed deadline. The initial
deadline of the run-of-the-river project was 2000 November. Thanks to several reasons
including the frequent labor strikes in the project site, the deadline was renewed for
2001 November. Having estimated that the works would not be over by then even, the Civil
Work contractor of the Kali Gandaki "A" project Impregilo S.P.A. is said to have
demanded with the NEA for the new deadline -- February 2002. That was before the
technicians of the project resigned. Now that almost all the technicians have walked away, the Italian contractor
would once again have a reason to extend the deadline of the project. "To extend the
deadline of the project, the contractor easily and immediately accepted our
resignations," the resigned technicians told a press meet earlier last week. "It
knew that our resignation can be a very good excuse to extend the project tenure." The technicians, most of them engineers, claimed that the contractor will now
have to hire new technicians who will first have to be trained before beginning the actual
work. And, even if the contractor completes the project within the stipulated time, it
will charge extra money for that, the technicians said. "Which means the national
coffer will be suffering ultimately." Why did all the technicians resign en masse? The episode began when Gopal
Prasad Mahato, an engineer then working with the project, mistakenly opened what the
Contractor claimed to be a confidential file. "When he was searching for a file to
change the Bikarm Sambat date to A.D., he happened to come across the file titled
Retrenchment Gratuity," a press statement issued by the technicians says. The management asked Mahato to resign immediately and the mid career engineer
did. But what sparked the anger among other technicians was the denial of the Italian
Contractor to provide an experience letter to Mahato. "They said they would give me a
letter defaming me," said Mahato. "I denied to receive such a letter." Then after began the mass movement in the project site. When things did not
work out even after holding talks, all the technicians opted to resign. Going by the
technicians' explanations, Mahato's case was only an impetus to the already enraged
project staff due to the "misbehavior of Italians at the project site." According to Surya Narayan Shrestha, an engineer who resigned together with
other technicians, Italians of a little above labor level would misbehave Nepalese
engineers at the project site. "The management had also begun to increasingly hire
foreign nationals even when Nepalese manpower was readily available." Whatever may have happened between the contractor and the technicians that
led to the latter's resignations, one thing has been for sure: Things are not moving
smoothly at the Kali Gandaki "A" project site. Going by the mood of the technicians, their mass resignation appears to be a
card they used to pressurize the management. But, the contractor seems to have found the
card to be more handy tool for its "project-tenure stretching" agenda. Also unanswered is the question why did the technicians not form a union and
fight for their cause since the beginning. Why did they get together only after Mahato's
case took place? Making the story more mysterious is the silence of the NEA that had
commissioned Impregilo S.P.A. With its ever extending deadline, observers have compare to
similarise the Kali Gandaki "A" project with those like Khimti and Bhotekoshi
Hydropower Projects, of the private sector -- widely believed to have taken the NEA for a
ride. |
Send your feedback to the
editor: spotligh@mos.com.np |