![]() |
||
|
||
KALI GANDAKI 'A' |
New Power On The Block The much-touted 144 MW
hydro-electricity project is all set to enter the central grid By SANJAYA DHAKAL After one and a half years of delay caused
by variety of reasons, the 144 Mega Watt (MW) Kali Gandaki "A" (KGA) project is
finally set to be completed within a few months. In fact, the project started conducting
test transmissions recently. A run-of-the-river project with daily
pondage system (for storage of water), the KGA is the flagship project undertaken by the
Nepal Electricity Authority (NEA) with cooperation from bilateral and multilateral
agencies. As most of the civil construction of the
KGA is now on the verge of completion, the project has started to test its capacity.
"Turn by turn, we have to test all the machines and turbines," said Dr. Jivendra
Jha, director, civil and planning department at the NEA's KGA project. According to him,
the KGA will start regular transmission to the national grid within the next two to three
months. The KGA has a daily peaking capability
during adverse hydrological conditions. Because of the provision of pondage system, its
capacity does not fluctuate in the dry and wet season. "Even during dry or lean
season, the project can run with full capacity during peak hours of power demand,"
said Dr. Jha. Another significance of KGA lies in its
financial layout. While the NEA had reached into take-or-pay agreement with projects like
Bhotekosi, and, that, too, in US dollars, KGA has no such problems. Besides, unlike
projects like Bhotekosi (36 MW) and Khimti (60 MW), whose capacity come down by more than
50 percent during dry/winter/lean season when power demand is considerably higher, KGA
provides power consistently. The KGA project is located on the Kali
Gandaki river in Syangja district in the western development region. A diversion dam
constructed 500 meters down the meeting point of Kali Gandaki river and Aandhi river makes
its water flow through a six-kilometer-long tunnel (with 7.4 m diameter) to the power
house located in Beltari. In Beltari, there are three turbines, each
with the capacity of 48 MW. After generating the electricity, the water is again flown
back to the river. The pond is spread over 65 hectares area. The project will feature an installed
capacity of 144 MW and generate about 842 GWh of electrical energy per annum. The power
from this project is connected to the central grid through 132 KV single circuit
transmission lines to sub-stations in Pokhara and Butwal. The KGA traces its origins to 1977-79, when
a Gandak Basin Master Plan was undertaken by an Australian company called Snowy
Mountaineering Engineering Company (SMEC the same company that is currently looking
at the prospects of developing the 720 MW West Seti project) with financial assistance
from the United Nations Development Program (UNDP). The SMEC had put KGA as the most attractive
hydel project in the whole Gandak basin. However, the project could not be developed then
owing to various reasons. Meanwhile, the development of Kulekhani I and II and Marsyangdi
took off. For more than a decade, KGA remained in
limbo. But in 1990s, when the Arun project of the Koshi basin was getting all the
attention, the KGA was silently being re-introduced. In 1991, UNDP once again provided
financial assistance for its detailed feasibility study, which was done by NorPower, a
Norwegian company. The NEA reached into agreement with an
Italian company Impregilo SPA in 15 July, 1997 for the civil construction. Although the
project was originally scheduled to be completed by the end of 2000, it was delayed by
more than one and a half years. "Previously, the wet test transmission
target was scheduled for 1 July, 2000 and electricity generation for September 2000, but
the wet test itself could take place only in 10 January 2002 and electricity generation in
March 2002," said Dr. Jha. A number of reasons resulted in the delay,
which raised the cost by up to Rs 7 billion from the amount the Impregilo originally
agreed for construction. While the engineer's total estimate for the KGA was put at US$
452.8 million, Impregilo SPA won the civil construction contract for much less.
Authorities now expect the project to cost nearly $384 million. "The project had to undertake the
tough river-diversion twice owing to various technical complications. It had to suffer
around 60 days of labor strikes. It encountered problems in jet-grounding. During the
tunnel construction, rock was found considerably weaker than our guess. Furthermore, a big
landslide occurred while the excavation for surge shaft was going on," Dr. Jha
recounts the reasons for the delay. The delay in time meant a proportional rise
in project cost. As 89 percent of the cost had to be paid in foreign exchange to the
contractor, the continuous depreciation of Nepalese rupee (from Rs 56.30 per $1 in 1997 to
more than Rs 75 now) did not help matters. "The justification of the cost rise would
become clear only after the project is completed and its finances audited properly,"
said Dr. Jha. At a time when the country is suffering
from power shortages, the connection of KGA to the national grid would certainly provide a
much-needed respite. The country can now look forward to generating electricity aimed not
only at its domestic market but abroad as well. Financial Plan Engineers' Estimate (total): US$452.8 million (including price
contingency, physical contingency, loss reduction component, project management and
interest during construction) Assistance: ADB: $160 million loan (C1, C3, consultancy
fee, experts' fee and environment mitigation cost) JBIC (formerly OECF): $160
million loan (C2, Lot 4, 5, 6 and 7) HMG/N: $32.8 million equivalent NEA: $100 million equivalent |
Send your feedback to the
editor: spotligh@mos.com.np |