![]() |
||
|
||
| OPNION |
Misconceived Upper Karnali Project By AB THAPA There is a growing realization that the
selection and implementation of development programs in Nepal are neither transparent nor
accountable. It was recently reported in the press that local representatives of donor
agencies like the World Bank and the Asian Development Bank were raising this issue in
official meetings. This is a matter of great concern to our country. Often,
decision-makers in developing countries do not hesitate to make excuses to carry out
programs that would poison their country's economy in the name of liberalization or
privatization. The Khimti project is one such example in Nepal. The much-hyped Melamchi
project, which would require each consumer in Kathmandu valley to pay about Rs.5,000 per
month for water supply, unless the government decides to pay from its own coffer a very
large sum of money as subsidy, could also be added to the list of such projects. The Upper Karnali Hydroelectric Project
could be one of the very few projects in the world to produce on a huge scale at an
exceptionally low cost peaking energy in great demand all across India. Unfortunately,
government institutions and donor agencies in Nepal are virtually unaware of this vast
potential. At present, we are on the verge of virtually ruining this potential by leasing
out this site to a private developer to build a relatively small simple diversion type
hydropower by comparison with its full-fledged version. There is an urgent need for
holding debates to be participated by few specially invited well-recognized experts in the
field of hydropower engineering on this issue before it is too late. The Karnali Bend The Karnali river makes a big loop in its
lower reach near a place called Asare. From here, the river flows in the south-east
direction for about 25 kilometers, after that, the river makes a complete reversal in its
direction. The river comes back to a point just two kilometers away from its earlier
position near Asare. There is a drop of about 150 meters in Karnali river bed elevations
between these two positions merely two kilometers away from one another. The project to
utilize this bend for power generation was originally known as the Karnali Bend Project.
Later the name was changed to Upper Karnali Project. Feasibility Studies The Karnali basin is the first to arouse
keen interest in Nepal's vast hydropower development study. There are several attractive
sites for the generation of cheap hydroelectric energy in this basin. In early 1960s an
agreement was signed between His Majesty's Government and the United Nations Development
Program for providing assistance to conduct a survey of the Karnali river and its main
tributaries culminating in a pre-investment report indicating hydroelectric potential of
the river as well as the best sites for hydropower development. The final feasibility
reports and general basin development report were submitted in February 1966. In the 1980s, further studies of the two
projects were carried out under the aegis of the World Bank. They are the feasibility
study of the Karnali Dam Project (Chisapani) and the pre-feasibity study of the Upper
Karnali Hydroelectric Project (Karnali Bend Site). Unfortunately, the scope of the Upper
Karnali Project study was deliberately made very narrow. The size of the project was
scaled down to be suitable to meet the Nepal's internal requirement completely
disregarding its vast potential to generate exceptionally cheap peaking energy for export
to India. The concept of the small Upper Karnali Project is very simple. It includes a
small diversion dam to provide daily regulation, a spillway for the passage of excess
water across the dam particularly during the floods, de-sanding facility, a power tunnel
across the Bend, and a power house at the downstream side of the Bend. The small Upper
Karnali project is not at all an inferior project by comparison with many others similar
in size. The proximity of the dam site from the power house helps to bring down the cost
of the delivery tunnel and its related structures like the surge chambers, although the
construction of a low-height diversion dam across a big river of the size of the Karnali
flowing in a narrow gorge is not an advantage. Unfortunately, this small diversion
project, as explained before, could preclude the viability of the large Upper Karnali
Storage project. This is a matter of prime concern. It might astonish many of us to learn
that the per unit investment cost (US dollars/ KW) of the Upper Karnali Storage project
could be much less even by comparison with such cost of the Karnali Chisapani High Dam
project. Therefore, this project could be far more attractive than any other projects for
the export of peaking power to India including the Karnali Chisapani Dam project. The Upper Karnali Storage Project It has been explained in the Upper Karnali
study report that a Karnali Bend storage hydro project could include a dam up to 260
meters in height. The most economical way of developing the full power potential of the
Karnali Bend would result from construction of a large storage dam on the eastern side of
the bend, a power tunnel across the bend and a generating station located on the western
side of the bend. If the Upper Karnali Storage project were developed to its full
potential, some 4000 MW of power at 25-percent capacity factor based on firm energy for
meeting the peaking demand could be installed. Comparison With Karnali Chisapani
Project The Upper Karnali Storage project and the
Karnali Chisapani Storage project both would be having waterways quite comparable in
length, but the Upper Karnali project would be operating at a head almost two times
greater than that of the project at Chisapani. It makes the Upper Karnali project far more
attractive for export of cheap peaking power to India than the Chisapani project. Reasons
for it are explained below. Of all the site characteristics, head is
the most important. Design guidelines, 1989 approved by the American Society of Civil
Engineers has given some simple reasoning that would help to explain why the Upper Karnali
project operating at a head about two times greater by comparison with the Chisapani
hydropower could be built at far less per unit installed capacity cost. "Very simply
if one doubles the head the quantity of water needed to produce a certain amount of energy
is halved, Thus, for like site energy development the conduit area and reservoir volume
are halved and further large cost reductions occur for powerhouse and machinery costs.
This fundamental consideration is at the root of the large cost reductions that occur at
higher heads." The lower investment cost means the generation cost of the electricity
would also be less. The Stage A study report of the Karnali
Chisapani Project shows that the increase in hydraulic head greatly helps to enhance the
net project benefit. It has been explained in the report that the incremental benefit
would be about six times greater than the incremental cost if the height of the Chisapani
dam is further raised over the present height fixed at 270 meters. It is stated in the
report that the dam height was limited at 270 meters for the reason that higher reservoir
levels and dam heights would cause the abutments of the dam to spread into the Banghar
Khola upstream and would severely constrain project development between the downstream toe
of the dam and the preferred spillway plunge pool location downstream. It is not
satisfactorily explained in the report why other sites further upstream suitable for much
higher dams were not considered for the optimization study. A Great Loss To Nation The Upper Karnali Storage project about
half the size of the Karnali Chisapani project could help to accrue our country enormously
large benefit from export of electric power at highly competitive rates. Such excellent
opportunity could turn into a desert mirage if we unwisely decided to lease out the
Karnali bend site to a private developer to build a relatively small simple diversion
project. It might well turn out that the Upper
Karnali storage project and the Upper Karnali simple diversion project are mutually
exclusive. We will be certain about it only after the completion of a full-fledged
detailed study of the Upper Karnali Storage project. Even in case these two projects are
not mutually exclusive of one another, it would not be justifiable to implement the simple
diversion project. It is the opinion expressed in the pre-feasibility report of the study
carried out under the aegis of the World Bank. The excerpt from that report is given
below. Even when assuming that the KR 1 A
run-of-river project (simple diversion project) is a sunk cost, it will be seen that a
single large power plant (4180 MW) associated with the major storage project is less
costly than the combined cost of smaller plant at the same location (3532 MW) and a second
power plant at the foot of the storage dam (408 MW) discharging directly into the KR 1A
run-of-river project head pond. Based on this assessment, it appears that the later
development of the major hydro storage project at Site KR 1 would cause the KR 1A
run-of-river project to be effectively discontinued. There may be limited opportunity for
secondary energy generation during the periods of spillage. Advice From Donor Agencies Nepal should always be very grateful to
donor countries and institutions for enormous economic assistance being provided to
develop our water resources. Nepal needs to be helped in future to establish close rapport
with leading foreign institutions particularly in the field of water resources engineering
to be constantly guided in planning and implementation of various programs so that our
country would not be misled to take decisions detriment to the genuine interest of our
people. Institutions like the International Center for Integrated Mountain Development
could also be directed to play more active role. |
Cover Story | Tihar | Politics |
New
Policies | Interview | Constitution | Encounter | Traffic
Flow | Art | Bhutan
Day |
Send your feedback to the
editor: spotligh@mos.com.np |