![]() |
||
|
||
| OPNION |
Kosi High Dam And 1997 Study Agreement By Dr. AB Thapa I was fully convinced
well in advance of the year 1996
when I was appointed to lead a
Nepalese team constituted to negotiate with
India about the Kosi Study Agreement that
the proposed Kosi Dam could become the
highest in the world. I had explained
about it in my study report entitled
Planning Kosi High Dam Project brought
out several years before the 1997
Indo-Nepal Kosi Study meeting. Many of us might be
astonished to learn that the installed
capacity of the Kosi Dam Hydropower Station
could reach 16 million KW or even more if
the evaluation criteria used in the
determination of the installed capacity of the
Karnali Project (Chisapani) is applied to the
Kosi High Dam Project too. According to the
detailed feasibility study the installed capacity
of the Karnali Project (Chisapani) is
only 10.8 million KW. Similarly the annual
power generation of the Karnali Project ( Chisapani)
is about 20 billion KWh, whereas in case
of the Kosi High Dam Project, such annual
generation could be about 30 billion KWh.
As of now the biggest hydropower station
already in operation in the whole world
is the 12.6 million KW Itaipu Hydropower
Station jointly built by the Governments of
Paraguay and Brazil. The 18 million KW
Three Gorges Project Hydropower Station in
China is still under construction. Thus among
the hydropower projects so far in operation
throughout the world the Kosi High Dam
Project could exceed all others in terms
of both the dam height as well as
the total installed capacity of the power
station, as a result we would not
be able to benefit from the previous
experience of building anywhere in the
world a hydropower project of a similar colossal
size. Research & Development Needless to say that
we would be encountering enormous difficulties
in planning and implementation of the Kosi
High Dam Project since it is going to
be one of the biggest projects in the
whole world. . In resolution of several such
problems, the Research & Development works would
be virtually indispensable. In several instances
the results of the Research & Development
would be required even to work
out the plan to conduct the
detailed study of this mammoth project.
Thus there would be a need to
spend a fairly long period to
complete such research and development works.
Realizing such bottlenecks that would
have further delayed the completion of
the detailed study, I had even
signed in my capacity as the Executive
Secretary, Water Energy Commission an agreement
in 1997 with the Kathmandu University to
facilitate the R&D necessary to
conduct the detailed study of the Kosi
High Dam Project and its navigation canal
component. Competent employees of the Ministry
of Water Resources willing to perform the
R&D works were to be engaged It
was agreed with the Kathmandu University that
on successful completion of the R&D the
researchers were to be awarded the M.Sc.
or the Ph.D. degrees. The proposed
on the job training was expected to be
an integral part of a running foreign
assistance program and thus the finance
for supporting this task was fully assured. .
Soon I retired from the government
service and, unfortunately, there was nobody
thereafter to push ahead this program. . Key Issues Raised
in 1997 Meeting There was not much
discussion about the size of the Kosi
High Dam Project in the 1997 Indo-Nepal
Kosi Study Meeting. Nevertheless, both sides
knew perfectly well that the Kosi High
Dam Project is going to be one of
the biggest in the whole world. The following
three key issues were raised in the
meeting. They were the Kosi flood
control, Sun-Kosi Dam Project and Kosi
navigation canal. India agreed to accept
our proposal on all three issues. Until few years back
the Indian Government was seen to be
drifting away from the facts that it is
absolutely indispensable to provide storage dams
in the basin to prevent the Kosi flood
disasters. The Indian Government was saying
that the Kosi flood control problem has
already been resolved after the completion of
the construction of embankments on both
sides of the Kosi River. . So
right at the outset of the meeting held
in Kathmandu to finalize the Kosi Study
Agreement, I had to give a brief
presentation on Kosi flood problems. The
presentation was quite helpful in explaining
our viewpoint on Kosi development. Later on
in course of discussions the leader
of the Indian team expressed off the
record that from now on they are fully
convinced of the fact that the biggest
benefit to accrue from the Kosi development
would be the flood control The study to construct
the Kosi High Dam is now firmly
tied up with the provision of a
165 km long navigation canal out of it
a 120 km long section of such navigation
canal would be in Indian territory. The
proposed navigation canal would be linking
Nepal with the seaport through Ganges,
Bhagirathi and Hoogly rivers The Kosi Study Agreement
1997 has shown beyond doubt that the
commencement of the construction of the Kosi
High Dam would be contingent upon the
prior implementation of the Sun-Kosi High Dam
Project on technical grounds. The Sun-Kosi High Dam
Project, regarded to be benefiting almost
exclusively Nepal, prominently figured in
the talks to finalize the 1997 Kosi Study
Agreement. Indian side had wanted somehow
to exclude the Sun-Kosi Dam Project from
the Kosi development study. They did not
want to get bogged down into the
relatively big Sun-Kosi Dam Project Ultimately
the Indian side was convinced that it is
no more possible to sideline the prior
implementation of the Sun-Kosi Dam Project
despite the fact that it would be a
project to serve almost exclusively Nepal. They
realized the fact that the construction
of the Kosi dam would be further
delayed if the construction of the
Sun-Kosi Dam Project is not completed in
time. As a result, the Indian side even
agreed to provide financial assistance to carry
out expeditiously the detailed study of the
Sun-Kosi Dam Project also. Indian Concept of
Kosi High Dam The Kosi had shifted
from east to west over 120 km within the
last 200 years, as a result, about 10,000 sq.
km was laid bare with sand deposit. The
idea of building the Kosi High Dam was
conceived in the past primarily to resolve
the worsening Kosi flood problem. A request
was made to build Kosi embankments in Bihars
Post War Plan. However, Indias
Central Government felt that a comprehensive
study of the entire range of possibilities
should be made before embarking on building
embankments. Central Government advanced
the idea of building the storage dams in
the Kosi basin for controlling the floods.
India started the study to build the Kosi
High Dam in 1946. India had even
circulated a preliminary report of the Kosi
High Dam Project. The Kosi High Dam Project
according to the study conducted by the
Government of India consists of a 269 meters
high and 710 meters long concrete gravity
dam about 2 km upstream of the Barahachhetra.
The installed capacity of the hydropower station
would be 3,000 MW. The project includes a
diversion barrage 969.9 meters long near Chatra, 8 km
downstream of the dam. There will be canal system
with three power houses with a capacity
of 300 MW. Kosi Reservoir Volume
Insufficient The nature of the
topography of the Kosi reservoir area is
completely different from that of the Karnali
storage reservoir (Chisapani). The proposed heights
of the Kosi as well as the Karnali
dams are virtually identical. The Kosi dam
height is 269 m similarly the Karnali
dam height is also 270 m. Despite the
fact that the height of both the dams
are almost the same, there is a vast
difference in volume of the storage reservoirs.
The gross storage volume of the Karnali
storage reservoir is about 39 billion cu. m
out of it the dead storage, regulating
storage and flood control storage would be
11 billion cu. m, 16 billion cu. m, and 12 billion cu. m
respectively. The total gross storage volume of
the proposed Kosi storage reservoir would
be only 13.45 billion cu. m out of it the
dead storage, regulating storage and the flood
control storage would be 4.08 billion cu. m, 7 billion cu.
m, and 2.37 billion cu. m respectively. Recent studies of the
Himalayan region provide a whole bunch of
information very useful for planning high dams.
Such information were extensively used
for detailed planning of the
Karnali High Dam. The Karnali studies
carried out at an enormous cost by a
consortium of renowned consulting firms
of several countries under the aegis
of the World Bank in close
consultation with the governments of Nepal and
India have greatly helped to
realize that compared to the earlier
perceptions the magnitude of the problems
to be actually encountered in dam
planning in the Himalayan belt would be
far more serious and also complicated.
This has been amply reflected in
finalization of the design of the Karnali
High Dam. As a result, it can be
said that the proposed Kosi dam height is
too small to be effective to control the
Kosi floods for a relatively long period.
We certainly would not go far wrong if
the gross storage volume calculated for the
determination of the Karnali high dam is
applied in approximately determining the height
of the Kosi dam also since in every
respect the Kosi is a bigger river than
the Karnali. A Panel of
Experts The river Kosi is
bigger than the Karnali in terms of the
total annual water flow, annual volume of
the sediments being carried into the Terai
from the mountains and the drainage area.
Thus, if it is presumed on the above grounds
that the total storage volume of the Kosi
reservoir by comparison with the Karnali
reservoir should at least be equal,
the total volume of the Kosi storage
reservoir would have to be 39 billion cu.
m. Needless to explain that the dam
height should be further raised to increase
the storage volume of the reservoir. If
the Kosi dam height is raised from 269 m
to 300 m, the total storage volume would
still be only about 19 billion cu. m.
Perhaps the dam height should be in
between 335 m and 350 m if the total
storage volume of the Kosi reservoir is
to be about 39 billion cu. m. At present
the highest dam in the world is the Ragun
dam in the former Soviet Union. This dam
is still under construction though it was
expected to be completed many years before. The Kosi Dam can be
expected to be the highest in the
whole world. Planning as well as the
implementation of the dam of this scale
is going to be a very big challenge. There
is an urgent need to constitute a panel
of few renowned experts at the very early
stage to help us prepare program to
conduct the detailed feasibility study. (Dr. Thapa writes on water resources) |
Send your feedback to the
editor: spotligh@mos.com.np |