![]() |
||
|
||
| OPNION |
Donors And Nepal's Melamchi Plan By AB Thapa It might not be
possible to totally disagree that our country's
failure to address the growing economic
problems is the key factor that has resulted in the
present unrest in Nepal. People's widespread
frustration can have disastrous consequences
for any country and it can even pose
serious threat to the world peace if it
spreads over several countries. The situation that
developed in Europe after the First World War
that led to the next World War is a
clear proof to it. The economic situation of Germany during
the first five years after the First World War made
the political situation even more precarious. Germany was not able
to meet reparations requirements, as a result France
invaded the industrial center of the Ruhr in 1923, seizing control of all its coal
deposits. Before July 1922, the value of the Reichsmark had already dropped from about 4
to 493 to the dollar, but during the next 16 months it plummeted to virtually
nil. The inflation was so high that
millions of marks were required to buy
even the most basic item. As a result, German
money frequently had more value as kindling than as
legal tender. The resulting inflation wiped out the savings, pensions, insurance,
and other forms of fixed income of most middle-class
and working-class Germans. In 1924 the Dawes Plan was implemented to
ease the German reparations. The worldwide depression of the 1930s, however, plunged
the country once more into disaster. Millions of unemployed Germans, disillusioned by
capitalist democracy, turned to the National Socialist German Workers' Party (NSDAP), the
party of National Socialism, or Nazism. By 1930 the Nazis were the second largest party in
the Reichstag A Lesson Learnt United States program of financial
assistance helped to rebuild European nations devastated by World War II
(1939-1945). It is commonly called the Marshall Plan, named after U.S. Secretary of State
George Catlett Marshall. After the war, Europe's agricultural and coal production had
nearly stopped, and its people were threatened with starvation. The United States must
have drawn lessons from the events that
followed the period after the First World
War. They must have realized that
they would have been completely left alone
and thus they would have found themselves
defenseless in the struggle against the
countries subscribing to principles completely alien
to them if the Europe is not helped
to become economic and political power. After careful planning, Marshall announced
in June 1947 that if Europe devised a cooperative, long-term rebuilding program, the
United States would provide necessary financial assistance. The Congress
of the United States appropriated more than $13 billion in aid. Seventy percent was spent
for goods in the United States. The Economic Cooperation Administration distributed the
money, and the Organization for European Economic Cooperation (OEEC) spent it. The largest
amounts of money went to Britain, France, Italy, and West Germany, in that order. The program achieved both its immediate and
long-term aims: When the aid ended in 1952, the region's industrial production stood 35
percent above prewar levels, and West Germany was independent, and economically booming.
In 1961, the OEEC was succeeded by the Organization for Economic Cooperation and
Development (OECD). The OECD broadened the scope of cooperation among member nations. Foreign Assistance to
Nepal After the advent of
democracy in 1951, Nepal has been receiving
generous financial and technical assistances
from several donor countries and international
development agencies like the IDA, ADB, KFW
etc to carry out various programmes to improve
the living condition of the people living
in our country. Many donors have fully realized
that Nepal is at the very bottom in
the list of the poor countries so
the economic condition of our country is too
weak to allow us to carry heavy burden
of foreign debts. As a result, such donor
countries have been providing us mostly aids
in grants. Apart from it, many donor countries
and international development agencies have been
helping us to implement different types
of programmes with utmost vigilance to
insure that full benefits would accrue to
Nepal from the programmes they are
handling. Foreign assistance has also been
channeled to Nepal through regional
institutions like the ICIMOD, IUCN etc. Nepal's Active
Participation Encouraged In the past, donors
had always been trying their utmost to
insure that various programmes taken up in
Nepal are in the best interest of our country.
They never failed to agree to incorporate
any positive amendments proposed from the
Nepalese side to the whole programme if
they were really in the interest of
our country. They always backed up
even if it would be awfully
difficult to accommodate such changes. A case
in point could be the Kankai Irrigation
Project. The ADB had provided assistance in
grants in 1970s to carry out the
feasibility study as well as the detailed
design including the preparation of the tender
documents. The ADB had agreed to provide
assistance in grant even to carry out the
detailed design in the hope that the
construction of the project could be
significantly advanced forward . As a result,
the entire design works including the
preparation of the tender documents were
completed in the home office of the
consulting firm appointed by the ADB and
thus the Nepalese side did not have
opportunity to be involved in the design works
Later on Nepalese side found that there
is a good scope to improve the design
of the Kankai Irrigation Project. It was
established that the capacity of the major
structures and the canal which constituted
roughly about 70 % of the total project
cost could be raised by 60 %
without any increase in the project cost
if the project design was substantially
modified. Despite the fact that the
construction tender had already been awarded
and the contractor had even started the
construction works at site, the ADB
concurred with the government proposal to
amend the entire design of the
canal system and structures. The joint effort of
the Ministry of Water Resources and
the engineering team selected by the
donors to carry out the detailed design
works had helped in the past to enhance
significantly the effectiveness of the
Marshyangdi Hydroelectric Project now in operation.
Attention of the Ministry of Water Resources
was drawn to the design of the
Marshyangdi Hydroelectric Project at that time
when the detailed design of that
project rated at 63 MW had already been
completed. The civil work tender documents were
ready and they were going to be issued
at any time to the pre-qualified
bidders. According to the recalculation of
the Ministry the proposed size of
the civil works would allow to have the
installed capacity of the power station
well over 63 MW. After a series of
correspondence between the Ministry and the
consultant's head office it was agreed to
come to a compromise to accept the
rated capacity at 69 MW. One of the
Marshyangdi Project officials stationed at Kathmandu
who is even now in the Government service
performed the role of the intermediary
facilitating the exchange of documents between
the Ministry and the consultants. Later on
the consultants appeared to have fully
realized the significance of the Ministry's
concern. They raised the capacity of the
electro-mechanical equipments of the Marshyangdi
project on their own well over 69 MW to
75 MW. Now the Marshyangdi hydropower can
generate 75 MW. The Melamchi
Mismanagement The strategy document of
the Ministry of Physical Planning (Dated November,
2000) explains about the inter basin transfer of
water from surrounding areas, which comprise
the diversion of all three rivers
of the Indrawati basin ( Melamchi, Yangri and Larke)
but not just only the Melamchi river. It
has also been clearly stated in the
UNDP supported Melamchi project study report
that around the time 2011 the total system
demand (in Kathmandu valley) is expected to
reach the total supply from in-valley surface sources
and Melamchi. After that the next stage
of the development of the Melamchi will be
required. This entails the diversion from the
Yangri and Larke. The whole country has
been waiting with greatness eagerness the
completion of the Melamchi plan since the last
10-12 years. Every activity of this project
was being closely watched by the residents
of the Kathmandu valley, by various
organizations established to protect the right
of the consumers, and most of all by
the Nepalese press playing avant-garde role
in defense of the interest of the
Nepalese people. Despite all these things the
concerned government agencies did not hesitate
to lease the Yangri and Larke rivers to
private developers for the development of
hydropowers. Surprisingly hardly any INGOs or
NGOs or the Nepalese press have raised
their voice against such decision. It was not
even asked why such decision to
lease the Yangri and Larke rivers for
power generation had to be taken. Despite
the eagerness of the donor countries and
institutions to help Nepal in every possible
way in the task of providing basic
facilities to common people, some of the
donors' representative are not seen to be
very keen on handling the Melamchi project
with great care. They seem resigned to
accept anything even if the Melamchi
project would prove to be a white
elephant. A New Opportunity It is a sheer luck
that the Melamchi planning mistake could
even now be corrected. For this purpose
the high head Langtang diversion
project now being studied by the NEA for
power generation should be slightly modified
and linked with the headwork of the
Melamchi tunnel. If the alignment of the
tunnel to draw Langtang water at Ghore
Tabela for power generation is changed and the water
after the power generation is led into
the Melamchi river as against the original plan
to discharge into the Trisuli river, there
might be even slight decrease in the
total combined cost of the Melamchi water supply
project and the Langtang power project.
However, such rerouting of the Langtang power
tunnel could open up completely new
vistas of possibilities for the generation of
cheap electricity. The proposed new plan
could allow to provide Melamchi water to
the residents of Kathmandu in abundant
quantity for free. It would be possible
to generate electricity mostly in dry seasons
when the demand for electricity is the
highest. What To Do The
Next? The whole concept of
the Melamchi tunnel would remain intact. A
brief study should be immediately carried out
to find out the most suitable cross sectional
area of the tunnel and also the most
desirable location for the entry point of
the Melamchi tunnel into the Kathmandu valley.
The original UNDP plan to build the
Melamchi tunnel power station should be revived.
After few such adaptations the present
Melamchi plan could be allowed to proceed. There is an urgent
need to act immediately to suspend the
license given to a private developer to
use a part of the lower reach of
the Langtang river for power generation.
After the construction of such small
scale Langtang power project, both alternatives
of the big scale Langtang development including
the one being studied by the NEA would be
precluded. It is explained about it in an
article published in the SPOTLIGHT on August 16,
2002 under the heading "Threat To Super
High Head Langtang Projects" It is really an
embarrassment to all of us Nepalese that one wing of our
government after finding the Langtang diversion
at Ghore Tabela to be an excellent medium sized high-head
hydropower project conducts very expensive studies to
implement that project whereas at the same
time another wing of the government virtually trying
to bring down that project leases that very site to a private
hydropower developer to build a small project
despite the fact that both those government
wings are under the same ministry. |
Send your feedback to the
editor: spotligh@mos.com.np |