![]() |
||
|
||
| OPNION |
Electricity Planners At Fault By AB Thapa Any future plan must
be based as far as possible on the
experience gained in the past. This has been
the practice everywhere in the world. Unfortunately
in Nepal we are very insensitive to realization
that our planning must take full advantage
of our own past experience and should
be supported by relevant studies carried
out at home and also in other
countries. Donors have been very
generous to Nepal in helping us to implement
various types of projects. They have also
spent a huge sum of money to carry out
studies which are presented in innumerable
volumes of reports submitted to our government.
Nobody is seen taking interest to read
carefully such reports in display in various
government libraries. Even those reports
that are highly valuable for our present
national plan gather dust in the shelves
of the libraries of the government departments.
At present our electricity sector is in
complete disarray because we never cared to
look behind and draw lessons from the
findings of our own past studies. An
interesting case to be presented here could
be the Kulekhani-3 episode because a
final decision to implement this project is
yet to be made. The way the JICA study (
1988 ) of the Kulekhani-3 project, proposed to
be developed to accrue primarily capacity
benefit, threw all of us into total
confusion shows that none of us have
seriously read the economic analysis contained
in the feasibility study reports of the
major projects such as the Karnali Chisapani,
Pancheshwor, Sapta-Gandaki etc. Kulekhani Power
Development It is said that the
hydroelectric power development potential of
the Kulekhani river was for the first time
explored by the Swiss-Nepal Team in 1956. It
was initially planned to effect the simple
diversion of the Kulekhani river into the
Rapti to utilize the enormous difference in
elevations between the two rivers to build a
high head power station. At that time storage
dam was not considered. A technical team
dispatched by the Government of Japan in 1963
carried out a more comprehensive study and
prepared a preliminary design report. In 1974, the feasibility
study of the Kulekhani hydroelectric
power projects was completed under the JICA
assistance. The study report recommended to
take up for implementation the Kulekhani-1
hydropower project. The construction of the
Kulekhani-1 project was completed in 1982
within the time stipulated in the feasibility
report. The project comprises of a 107
meters high rock fill dam, a reservoir with an
effective storage volume of 73.3 million cm. on
the Kulekhani river, and a power station
with an installed capacity of 60 MW on the
Rapti river operating at a water head of
over 600 meters. The study of the
Kulekhani-2 hydropower project was carried out
side by side with the construction of the
Kulekhani No-1 project. The regulated flow of
the Kulekhani river is directly drawn into the
headrace tunnel of the Kulekhani-2 project
from the tailrace of the Kulekhani-1 power
station. The natural flow of the Mandu river, a
tributary of the Rapti, is also drawn into
headrace tunnel of Kulekhani-2 project. The installed
capacity of the Kulekhani-2 power station
operating at a head of over 300 meters
is 32 MW. The construction of the Kulekhani-2
power project was completed in 1986. The feasibility study of
the Kulekhani-3 hydropower project was completed in
May, 1988 as the last project in the
integrated development of the Kulekhani hydropower
system. Very recently Water Energy Commission
has put forward a new proposal to divert
the Langtang, Melamchi, Yangri, Larke and Balephi
rivers through Kathmandu valley into the
Kulakhani storage reservoir for power generation.
Such diversion would allow the Kulekhani
hydropower projects to operate in full capacity
throughout the year. However, it would be
necessary to build a new hydropower
project running in parallel to the existing
Kulekhani- 1 & 2 hydro power projects to
fully utilize the stored water in the
Kulekhani reservoir in excess to the
requirements of the existing Kulekhani
hydropower plants. A single hydropower station
operating at a head over 1000 meters
directly drawing water from the Kulekhani storage
reservoir and discharging into the Rapti near
Bhainse could be built. The total length
of the tunnel of this project would be
about 13 kilometers. The small reregulation
reservoir of the Kulekhani-3 project could be
used to cushion the abruptly varying high
discharges from the power houses against river
bed erosions if the total installed capacity
of the Kulekhani system power stations is
significantly raised to cover extreme
peak loads. The proposed diversion of the
northern rivers into the Kulekhani system is
also linked with the plan to augment the
water availability in the Kathmandu valley. Kulekhani-3 Power
Project The feasibility study of
the Kulekhani-3 Project had been carried out
under the JICA assistance. Few findings
of that study is presented hereinafter. The
power supply situation had greatly worsened, as
a result the NEA started the load shedding
in whole country including Kathmandu city from
November 1st 1992. The duration of the power
shedding was 2 hours on the peak load
every day. Additional countermeasures were required
to avoid the continuance of power
shedding because there was a huge gap
between the power supply capacity and the
expected high growth of demand, particularly
during the peak load time in dry season, from
November to March. Despite the huge potential
for hydropower development in Nepal,
there were limited possibilities for the urgent
development. Most of the identified projects
were not yet fully ready to go into
construction any time soon. In addition, many of
them were planned as the run-of-river type
without the provision of daily storage
facility. Such projects could not fulfill
our requirements to meet the demand for
the peak load. The diesel powered or
gas turbine plants are suitable for the
supply of electricity to meet the peaking
demand, however, the NEA hesitated to build
such thermal power plants with big installed
capacity. The Kulekhani-3 Hydropower Project with an
installed capacity of 50 MW ( it could go up
to 75 MW if the peaking period is
only 2 hours) was certainly the
most appropriate project in every respect. The
feasibility study was already completed in 1988.
The project planned as an extreme
peaking power station to generate electric
power exclusively in evening time lasting
3 hours or even less in dry season
utilizing the existing Kulekhani reservoir
storage with an effective capacity of 73.3
million cm perfectly matched against the
NEA's need for generation expansion. Those of us
involved in planning have often felt that
in our country it is rather easy to
identify a good hydropower project suitable to
generate electricity to meet the base load
demand. On the contrary, the peaking
power supply particularly in dry season
is the most critical problem and thus
this issue needs to be very carefully addressed
in taking decision to select such
hydropower projects. It hardly needs to be
explained that it would always be
far economical to use the unutilized
existing capacity that would be available free
of cost rather than to provide a
new one. It implies that in case of the
Kulekhani system we should try to
make maximum usage of the existing
reservoir storage that would allow us
to generate electricity during the
critical dry months when the demand for
the electricity is the highest. The Kulekhani-3
Hydropower project has clear advantage over
all other similar projects and thus it
was found at that time to be the
most suitable project to meet the peak
power shortage. NEA's Faulty Perception The recommendation made
by the JICA team to implement the
Kulekhani-3 hydropower station with an installed
capacity of 50 MW was absolutely correct. At
that time in our national grid the
shortfall in capacity was over 20% whereas
the shortfall in energy was merely around
2%. A brief study carried out
in the Water Energy Commission had
recommended to increase the capacity of the
Kulekhani-3 hydropower even up to 75 MW
because at that time the duration of the
load shedding was only 2 hours and the
economic benefit would have been much higher
by comparison with the 50 MW alternative.
The 75 MW or 50 MW Kulekhani-3 projects would
be having very high capacity
benefit but the energy benefit is not
significant. Unfortunately the idea of capacity
benefit came as a total surprise to the
NEA. The NEA regarded that the capacity
benefit is something fictitious and thus it
could be ignored. So they went completely
against the proposal of the JICA study
team, as a result it was decided at
that time not to implement the Kulekhani-3
project. However, they are now seen lured
by the 13 MW capacity Kulekhani-3 project
operating in tandem with the Kulekhani- 1&2
power stations that has somewhat higher energy
benefit despite the fact that the capacity
benefit of this alternative is quite low. Lack of understanding of
power engineering economics could have grave
consequences for the sustainability of the
NEA. At present the NEA is running into
great surpluses of the seasonal energy which
is now almost completely wasted. Hydropower
projects built in NEA's choice have to be
operated continuously round the clock like the
coal based thermal power stations despite the fact
that the country could offer any number
of more suitable hydropower projects. All
troubles of the NEA emanate from
the facts that responsible person in NEA are
quite unaware of the power engineering
economics problems and thus they easily fall
victim to cunning foreign hydropower developers
entering into Nepal to become quickly
very rich. Let us analyze the significance
of the capacity benefit in global context
that indeed would be equally applicable in he
context of our country also. Dependable Capacity
Benefits Providing a source of
dependable peaking capacity is one of the
basic objectives and accomplishments of hydropower
stations like the Kulekhani-3 ( 50 to 75 MW in
capacity) or pumped storage plants. By
providing a dependable source of capacity during peak
power demand periods, the reliability of the
power supply system is increased. At present pump storage
plants are being built everywhere in the
world including India. Needless to say that
such pump storage plants are built because
they are highly feasible. The pump storage
plants are built to provide exclusively
capacity benefit. Foreign experts dealing in power
engineering must be greatly surprised to find
that those of us working in the NEA or
EDC have hardly any knowledge about capacity
benefits or, else the NEA would not have been
forced to confront the adverse situation
whereby it spends now about 50% of it
revenue to buy electricity from the private
developers perhaps more than 2/3 of such
energy is completely wasted. The power benefit
must be calculated as the sum of
the capacity benefit and the energy benefit.
The economics of the modern pump storage
engineering is based on the fact that the
power benefit of such pump storage plant
can be high despite the fact that the
energy benefit is negative because it can
roughly be said that about 3 KWh
electricity is spent to produce only 2 KWh
electricity. Indian Experience It is very difficult
to find good sites for hydropower projects
like the Kulekhani-3 project suitable to meet
the peak load of the system. The next
alternative is the pumped storage plants despite
the fact that there is a net energy
loss in the system. It is said that
realizing the great importance of the role to
be played by the pumped storage power plants in the
Indian power system, the Central Electricity
Authority (CEA ) has undertaken a very extensive
systematic survey of the entire country with a
view to identify suitable sites which may
help in development of economical pump storage
schemes with a total installed capacity of
94000 MW. |
Send your feedback to the
editor: spotligh@mos.com.np |