![]() |
||
|
||
| OPNION |
Devastation Of Upper Karnali Project By AB Thapa All of us know
very well the terrible September eleven event
that shook the whole world. The New York
twin tower was blown up by Al Qaida.
If it is asked why the twin tower
was blown up, perhaps we might get
a very simple answer. It
could be an act of revenge. Now
let us take a some what different case.
Let us suppose the USA Government itself
blew up the twin tower or let us
suppose the Saudi Arabian Government bombed all
her oil fields. How the news
would have been received throughout the world,
if the USA and the Saudi Arabian
Governments had actually done so?
Certainly, every sensible man would have
definitely felt that the concerned decision makers
must have gone mad. However, nobody would ever
believe that such thing can really happen.
Unfortunately our country is very soon going
to be victimized for our similar unforgivable
doing if some of our decision makers are
not dissuaded in time from carrying out
such act utterly harmful to our
nation. We are soon going to devastate
the 4180 MW mega Upper Karnali power project
which might be one of the best
projects even in the whole world to
generate exceptionally cheap peaking hydroelectric
power on an enormously large scale. There is
a great demand for peaking electric power
in India. Moreover the peaking electric power
fetches much higher price. In 1991 the
Thai Government was paying Laos Government US Cents
5.8 per KWh for peaking energy, whereas such
price for the remaining hours was only about US
Cents 2.98 per KWh. The electricity
produced by the mega Upper Karnali storage
project could be exported to India to the
mutual advantage of both Nepal and India. Exceptionally Favourable
Topography The Karnali river makes
a big loop in its lower reach near a
place called Asare. From here the river flows in
the south-east direction for about 25
kilometers, after that the river makes a
complete reversal in its direction. The river
comes back to a point just two
kilometers away from its earlier position
near Asare. There is a drop of about
150 meters in Karnali river bed elevations
between these two positions merely two
kilometers away from one another. The project
to utilize this bend for power generation
was originally known as the Karnali Bend
Project. Later on the name was
changed to Upper Karnali Project. Two Mutually Exclusive
Upper Karnali Projects The Karnali basin
is the first to arouse keen interest in Nepal's
vast hydropower development study. There are several
attractive sites for the generation of cheap
hydroelectric energy in this basin. In early
1960s an agreement was signed between HMG
of Nepal and the UNDP for providing
assistance to conduct a survey of the Karnali
river and its main tributaries culminating in
a pre-investment report indicating hydroelectric
potential of the river as well as the
best sites for hydropower development. The
final feasibility reports and general basin
development report were submitted in February, 1966. In 1980s further
studies of the two projects were carried
out under the aegis of the World Bank. They
are the feasibility study of the
Karnali Dam Project (Chisapani) and the
pre-feasibility study of the Upper Karnali
Hydroelectric Project ( Karnali Bend Site). Unfortunately,
the scope of the Upper Karnali Project
study was deliberately made very narrow.
The size of the project was scaled down
to be suitable to meet the Nepal's
internal power requirement completely disregarding
its vast potential to generate exceptionally
cheap peaking energy for export to India.
Thus there are at present two Upper
Karnali projects. They are the 300 MW Upper
Karnali Project and the 4180 MW mega Upper
Karnali Storage Project. These two projects are
mutually exclusive. In other words, it
would not be possible later on to build
the 4180 MW mega Upper Karnali Project without
sacrificing the small 300 MW small Upper Karnali
Project. The relevant excerpt from the WORLD
BANK supported Upper Karnali project study
report is presented hereinafter. World Banks
Disapproval of Small Upper Karnali The World Bank
has disapproved of the small Upper Karnali project.
The relevant excerpt from the World Bank supported
Upper Karnali project study report is presented
below. Even when assuming
that the KR 1 A run-of-river project ( small 300 MW
Upper Karnali project) is a sunk cost, it will be
seen that a single large power plant (4180 MW)
associated with the major storage project is
less costly than the combined cost of smaller
plant at the same location (3532 MW) and a
second power plant at the foot of the storage dam (
408 MW) discharging directly into the KR 1A run-of-river
project head pond. Based on this assessment,
it appears that the later development of the
major hydro storage project at Site KR 1 ( mega
Upper Karnali Project) would cause the KR 1A
run-of-river project to be effectively discontinued.
There may be limited opportunity for secondary energy
generation during the periods of spillage. Demand for Peaking
Power in India At present India
is experiencing an acute shortage of peaking
energy. At the beginning of the Eight Plan,
the total peaking shortage was 20% whereas the
energy shortage was only 9% of the total
power generation. The thermal and nuclear power
stations are suitable to supply electricity to
meet the base load demand of the
system. It is not economic to use them
to supply peaking energy. Gas turbines can
be used to meet the peak load demand
because of low specific investment costs and
quick start up. However, the efficiency is
limited due to the high exhaust gas
temperature of the turbine. India is making
every effort to improve the hydrothermal mix
for ensuring better system operating condition.
However, the share of hydropower in the
overall power generating capacity has steadily
declined since the last few decades. The share
of the hydropower in the overall power
generating capacity was 50.6% in 1963. But
few years before it has come down to
only 25.66%. Pumped Storage Schemes Most of the good
sites for the hydropower development have
already been developed in the Northern India.
There are even now several good sites
for hydropower development in the North-Eastern
India which have not as yet been
used. However, such sites are at locations
far away from the load centers. As a
result, the Government of India in recent
years had to embark on a
plan to develop the pump storage schemes Pumped storage schemes
are provided for the generation of peaking
power, even though there is a net energy
loss in the system because more energy is
consumed in pumping than can be produced
by the turbines. The cycle efficiency of a
pumped storage plant can usually be between
60 and 70 percent. It implies that such
a plant consumes abut three units of
electricity to produce only two units
during the peak hours. The cost of
the peaking energy produced by a pumped
storage plant will have to take into
account the investment to be made in the
construction of the pumped storage plant.
The per unit capacity investment cost of a
pumped storage plant can be comparable to
the cost of a similar hydropower located at
a favorable site. So far 56 major
pumped storage schemes with a total installed
capacity of 94,000 MW are reported to have
been identified in India. Already few
pumped storage schemes such as the Nagarjun
Sagar (700 MW), Kadampani (400MW), Kadana (240MW), Panchit (40MW), Paithan,
and Ujjani are either in operation or
under various stages of construction. Bids were
being evaluated some years ago by the West
Bengal authorities for a civil work contract
for the 900 MW pumped storage facilities
at Purulia on the Ayodhya hills. Three
other pumped storage facilities of similar
capacity are being planned. The pumped
storage at Sardar Sarovar (1200 MW) and Tehri
(1000MW) are planned for construction in
near future. Rush to Grab
small Upper Karnali Project The concept of
the small 300 MW Upper Karnali Project is
very simple. It includes a small diversion
dam to provide daily regulation, a spillway
for the passage of excess water across the
dam particularly during the floods, desanding
facility, a power tunnel across the Bend, and
a power house at the downstream side of
the Bend. The small Upper Karnali project
is a very attractive project by
comparison with many other
hydropower projects similar in size, as a
result, recently some private developers were
trying hard to acquire it. The proximity
of the dam site from the power
house helps to bring down the
cost of the delivery tunnel and its
related structures like the surge chambers
although the construction of a low height
diversion dam across a big river of the
size of the Karnali flowing in a
narrow gorge is not an advantage.
Unfortunately this relatively small 300 MW
project would preclude the 4180 MW
mega Upper Karnali Storage project. It
indeed is a matter of great
concern. It might astonish many of
us to learn that the per
unit investment cost ( US Dollars/ KW ) of the
4180 MW mega Upper Karnali project
would be far less than such
cost of the 10800 MW Karnali Chisapani
High Dam project. Thus this project
could be the most attractive
hydropower project for the export of
peaking power to India in near future Karnali Chisapani vs
mega Upper Karnali The Upper Karnali
Storage project and the Karnali Chisapani
Storage project would be having
waterways quite comparable in length ( about 2
km), but the Upper Karnali project would
be operating at a head almost
two times greater than that of the
project at Chisapani. It makes the Upper
Karnali project far more attractive for
export of cheap peaking power to India
than the Chisapani project. Reasons for it
are explained below. Of all the site
characteristics, head is the most important.
Design guidelines, 1989 approved by the American
Society of Civil Engineers has given some
simple reasoning that would help to
explain why the Upper Karnali project
operating at a head about two
times greater by comparison with the
Chisapani hydropower could be built at
far less per unit installed capacity
cost. "Very simply if one doubles the head
the quantity of water needed to produce a
certain amount of energy is halved. Thus, for like
site energy development the conduit area and
reservoir volume are halved and further large
cost reductions occur for powerhouse and machinery
costs. This fundamental consideration is at
the root of the large cost reductions
that occur at higher heads." Needless to
mention that the lower investment cost means
the generation cost of the electricity would
also be less. The Stage A
study report of the Karnali Chisapani
Project shows that the increase in
hydraulic head greatly helps to enhance
the net project benefit. It
has been explained in the
report that the incremental benefit
would be about six times greater
than the incremental cost if
the height of the Chisapani dam is
further raised over the present height
fixed at 270 meters. It is stated in
the report that the dam height was
limited at 270 meters for the reason
that higher reservoir levels and dam
heights would cause the abutments of the
dam to spread into the Banghar Khola
upstream and would severely constrain project
development between the downstream toe of the
dam and the preferred spillway plunge
pool location downstream. It is not satisfactorily
explained in the report why other
sites further upstream suitable for
much higher dams were not considered
for the optimization study. In Conclusion The mega Upper Karnali project could play very big role in uplifting the poverty ridden economy of our country in very near future. Thus, we should refrain from doing anything that would harm this project. |
Send your feedback to the
editor: spotligh@mos.com.np |