![]() |
||
|
||
| OPNION |
Power Export And Upper Karnali Project By AB Thapa Nepal has been hoping
since a long time that in near future
it would be possible to export on a
very large scale hydroelectricity produced in our
country. Unfortunately our concerned institutions
never seriously cared to explore the foreign markets
for our power, despite the fact that
some of the studies carried out
under the aegis of the donor agencies do
provide a good deal of information. It would be
explained hereinafter that the full-scale Upper
Karnali Project could be the best among all
projects studied so far for the export of
cheap power to India. Astonishingly, neither
the Water Resources Ministry nor the Planning
Commission appear to be aware of it. As
a result, the Ministry of Water Resources
is doing its best to implement the
simple diversion type Upper Karnali Project
that would ruin the prospect for the
generation of electricity on a large
scale for export to India at a
highly competitive price to the benefit
of both the countries. Indias Power
Market At present India is
experiencing an acute shortage of peaking
energy. At the beginning of the Eight Plan,
the total peaking shortage was 20% whereas the
energy shortage was only 9% of the total
power generation. The thermal and nuclear power
stations are suitable to supply electricity to
meet the base load demand of the
system. It is not economic to use them
to supply peaking energy. Gas turbines can
be used to meet the peak load demand
because of low specific investment costs and
quick start up. However, the efficiency is
limited due to the high exhaust gas
temperature of the turbine India is making every
effort to improve the hydrothermal mix for
ensuring better system operating condition. However,
the share of hydropower in the overall
power generating capacity has steadily declined
since the last few decades. The share of
the hydropower in the overall power
generating capacity was 50.6% in 1963.
But few years before it has come
down to only 25.66%. Pumped Storage Schemes Most of the good
sites for the hydropower development have
already been developed in the Northern India.
There are even now several good sites for
hydropower development in the North-Eastern
India which have not as yet been
used. However, such sites are at locations
far away from the load centers. As a
result, the Government of India in recent
years had to embark on a
plan to develop the pump storage schemes Pumped storage schemes
are provided for the generation of peaking
power, even though there is a net energy
loss in the system because more energy is
consumed in pumping than can be produced
by the turbines. The cycle efficiency of
a pumped storage plant can usually be
between 60 and 70 percent. It implies
that such a plant consumes abut three
units of electricity to produce only two
units during the peak hours. The cost
of the peaking energy produced by a
pumped storage plant will have to take
into account the investment to be made in
the construction of the pumped storage
plant. The per unit capacity investment
cost of a pumped storage plant can be
comparable to the cost of a similar hydropower
located at a favorable site. So far 56 major
pumped storage schemes with a total installed
capacity of 94,000 MW are reported to have
been identified in India. Already few
pumped storage schemes such as the Nagarjun
Sagar (700 MW), Kadampani (400MW), Kadana (240MW), Panchit (40MW), Paithan,
and Ujjani are either in operation or
under various stages of construction. Bids were
being evaluated some years ago by the West
Bengal authorities for a civil work contract
for the 900 MW pumped storage facilities
at Purulia on the Ayodhya hills. Three
other pumped storage facilities of similar
capacity are being planned. The pumped
storage at Sardar Sarovar (1200 MW) and Tehri
(1000MW) are planned for construction in near
future. Upper Karnali Storage
Project The Upper Karnali Storage
Project could be ranked at the very top
among all hydropower projects identified so
far in Nepal including the Karnali (Chisapani) High
Dam Project for the generation of cheap
peaking energy. The total installed capacity of
this power station could be about 4,000 MW at
25% capacity factor. Unfortunately, the Government
institutions and the donor agencies in Nepal
are virtually unaware of this vast
potential. At present we are on the
verge of ruining this potential by leasing out
this site to a private developer to build a
relatively small simple diversion type hydropower with a
capacity of about 300 MW There is an
urgent need for holding debates to
be participated by few specially
invited well recognized experts in
the field of hydropower engineering on
this issue before it is too late. The Karnali Bend The Karnali river makes a
big loop in its lower reach near a place
called Asare. From here the river flows in the
south-east direction for about 25 kilometers,
after that the river makes a complete
reversal in its direction. The river comes
back to a point just two kilometers
away from its earlier position near Asare.
There is a drop of about 150 meters
in Karnali river bed elevations between
these two positions merely two kilometers
away from one another. The project to
utilize this bend for power generation was
originally known as the Karnali Bend Project.
Later on the name was changed
to Upper Karnali Project. Feasibility Studies The Karnali basin is
the first to arouse keen interest in Nepal's
vast hydropower development study. There are several
attractive sites for the generation of cheap
hydroelectric energy in this basin. In early
1960s an agreement was signed between HMG
of Nepal and the UNDP for providing
assistance to conduct a survey of the Karnali
river and its main tributaries culminating in
a pre-investment report indicating hydroelectric
potential of the river as well as the
best sites for hydropower development. The final
feasibility reports and general basin development
report were submitted in February, 1966. In 1980s further studies
of the two projects were carried out
under the aegis of the World Bank. They are
the feasibility study of the Karnali
Dam Project (Chisapani) and the pre-feasibility
study of the Upper Karnali Hydroelectric
Project ( Karnali Bend Site). Unfortunately, the
scope of the Upper Karnali Project study
was deliberately made very narrow. The
size of the project was scaled down to
be suitable to meet the Nepal's internal
power requirement completely disregarding its
vast potential to generate exceptionally cheap
peaking energy for export to India. The
concept of the small Upper Karnali Project
is very simple. It includes a small
diversion dam to provide daily regulation, a
spillway for the passage of excess water
across the dam particularly during the floods,
desanding facility, a power tunnel across the
Bend, and a power house at the downstream
side of the Bend. The small Upper Karnali
project is not at all an inferior
project by comparison with many
other hydropower projects similar in
size. The proximity of the dam site
from the power house helps to
bring down the cost of the
delivery tunnel and its related structures like
the surge chambers although the construction of
a low height diversion dam across a
big river of the size of the Karnali
flowing in a narrow gorge is not an
advantage. Unfortunately this small diversion project
as explained before could preclude the
viability of the full-scale Upper Karnali
Storage project. It indeed is
a matter of great concern. It
might astonish many of us to
learn that the per unit investment
cost ( US Dollars/ KW ) of the Upper Karnali
Storage project could be much less than
such cost of the Karnali
Chisapani High Dam project. Thus this
project could be the most
attractive hydropower project for the
export of peaking power to India
among all projects identified so far in
Nepal including the greatly publicized Karnali
Chisapani Dam project. The Upper Karnali
Storage Project It has been
explained in the Upper Karnali study report
that a Karnali Bend storage hydro project
could include a dam up to 260 meters in
height. The most economical way of developing
the full power potential of the Karnali Bend
would result from construction of a large
storage dam on the eastern side of the
bend, a power tunnel across the bend and
a generating station located on the western
side of the bend. If the Upper
Karnali Storage project were developed to its
full potential, some 4000 MW of power at
25% capacity factor based on firm energy for
meeting the peaking demand could be
installed. Comparision With
Karnali Chisapani Project The Upper Karnali Storage
project and the Karnali Chisapani Storage
project both would be having waterways
quite comparable in length, but the
Upper Karnali project would be operating
at a head almost two times
greater than that of the project at
Chisapani. It makes the Upper Karnali project
far more attractive for export of
cheap peaking power to India than the
Chisapani project. Reasons for it are explained
below. Of all the site
characteristics, head is the most important.
Design guidelines, 1989 approved by the American
Society of Civil Engineers has given some
simple reasoning that would help to explain
why the Upper Karnali project operating
at a head about two times
greater by comparision with the Chisapani
hydropower could be built at far
less per unit installed capacity cost.
"Very simply if one doubles the head
the quantity of water needed to produce a
certain amount of energy is halved, Thus, for like
site energy development the conduit area and
reservoir volume are halved and further large
cost reductions occur for powerhouse and machinery
costs. This fundamental consideration is at the
root of the large cost reductions that
occur at higher heads." Needless to mention
that the lower investment cost means the
generation cost of the electricity would also
be less. The Stage A
study report of the Karnali Chisapani
Project shows that the increase in
hydraulic head greatly helps to enhance the
net project benefit. It has
been explained in the report
that the incremental benefit would
be about six times greater than
the incremental cost if the
height of the Chisapani dam is
further raised over the present height
fixed at 270 meters. It is stated in
the report that the dam height was
limited at 270 meters for the
reason that higher reservoir levels and
dam heights would cause the abutments of
the dam to spread into the Banghar
Khola upstream and would severely constrain project
development between the downstream toe of the
dam and the preferred spillway plunge pool
location downstream. It is not satisfactorily
explained in the report why other
sites further upstream suitable for
much higher dams were not considered
for the optimization study. A Great Loss To
Nation The Upper Karnali Storage
project about half the size of the Karnali
Chisapani project in terms of annual
electricity generation could help to accrue our
country enormously large benefits from
the export of electric power at highly
competitive rates. Such excellent opportunity
could vanish if we unwisely decided
to lease out the Karnali bend site
to a private developer to build a
relatively small simple diversion project. It might well turn
out that the Upper Karnali storage project
and the Upper Karnali simple diversion
project are mutually exclusive of one another.
We will be certain about it only
after the completion of a full-fledged
detailed study of the Upper Karnali
Storage project. Even in case these two
projects are not outright mutually exclusive of
one another, it would not be justifiable
to implement the simple diversion project. It
is the opinion expressed in the
pre-feasibility report of the study carried out
under the aegis of the World Bank.
The excerpt from that report is given below. Even when assuming that
the KR 1 A run-of-river project (simple diversion project)
is a sunk cost, it will be seen that a single
large power plant (4180 MW) associated with the
major storage project is less costly than the
combined cost of smaller plant at the
same location (3532 MW) and a second power plant at
the foot of the storage dam ( 408 MW) discharging
directly into the KR 1A run-of-river project head
pond. Based on this assessment, it appears
that the later development of the major hydro
storage project at Site KR 1 would cause the KR
1A run-of-river project to be effectively
discontinued. There may be limited opportunity for
secondary energy generation during the periods of spillage. Advice From Donor
Agencies Nepal should always be
very grateful to donor countries and
institutions for their valuable assistance in
development of our water resources. At present
Nepal urgently needs to be helped to
establish close relationship with various
leading foreign institutions working in
the field of water resources engineering.
Such relationship would provide us opportunities
to be constantly guided in proper
planning and implementation of various
programs, as a result, our country would not
go wrong in taking decisions in
the genuine interest of our people.
Institutions like the ICIMOD could also
be directed to play more active role. |
Send your feedback to the
editor: spotligh@mos.com.np |