http://www.nepalnews.com
spotlogo2.jpg (6318 bytes) VOL. 24, NO. 05, AUGUST 06 -  AUGUST 12  2004 ( SHRAWAN 22, 2061 B.S. )
OPINION

Bagmati River Conservation;  A New Approach

By Dr. AB Thapa

At present the Bagmati River  has virtually  turned  into city drain.  Residents of  the Kathmandu  valley  as  well  the large multitude  of  peoples  coming  to  Pashupatinath  Temple  each  day for worshipping  from  all  over  the  world  are  appalled  at  the  miserable  sight  of  the  holy  Bagmati  River.  It  can  hardly be denied  that the  water  scarcity  is  the  prime  cause  of  complete  deterioration  in   condition  of  the  Bagmati  River.  Unfortunately until  now  we  do  not  have  any  satisfactory  plan  to  resolve  this  serious  problem.  We  are  pinning  our  hopes  on  much  publicized  Melamchi  Project,   but  it  is  all  eyewash:  the  Melamchi  water  will  not  even  reach  Pashupatinath  Temple  area  in  dry  season.   According  to  the  Melamchi  Project  report  from  2011  onward  the  entire  Melamchi  dry  season  flow would  have  to  be  tapped  to  meet  the  growing  demand  for  water  supply  in  the  Kathmandu valley.

Fortunately  there  is  a  good  solution   to  resolve  the  Bagmati  River  conservancy  problem.  It  would  be  possible  to  transform  the  Bagmati  into  a  medium  sized  river   that  would  be  carrying  a  discharge  of  about  10  to  15  cumecs  even  in  the  driest  month. Many of  us might  be  astonished  to  learn  that  the  proposed   Bagmati  flow  augmentation  program  would  not  at  all  be  a financial  burden  on  residents  of  the  Kathmandu  valley.  Full  cost  of  the  project  could  be  recovered  from  the  sale  of  the  cheap hydro electricity.   The  generation  cost  of  the  electricity  would  be  very  low,  as  a result,  it  would  even  be  possible  to  lower   the  present electricity  tariff  which  might  be  among  the  highest  in our  region.

It  would  be  possible  to  greatly  enhance  the  feasibility  of  the proposed  Melamchi  Project  if  this  project  is  coupled  with  the  modified  Langtang  Project  which  is  not at  all  a  very  big  project.  The  whole  plan  would  comprise  of  the  three   steps.   (1) Diversion of  the  Langtang  River  into  the  Melamchi  for  generation  of  cheap  electricity.  (2) The  28 km  long  proposed  Melamchi Project  tunnel  would  deliver  the  combined  flows  of  the  Langtang  and  the  Melamchi  rivers  into  the  Bagmati  River near  Sundarijal.   It  would  not  be  necessary  to  enlarge  the size  of  the  Melamchi  tunnel  to  deliver  the  combined  flow of  the  Melamchi and  Langtang  rivers.  The  cross-sectional  size  of  the  proposed  Melamchi  tunnel  is  too  large  It  can  easily  carry  the combined  flow of  the  Melamchi  and the Langtang rivers. The  augmented  Bagmati  River  would  be  able  to  flush  wastes held  in suspension  across  the  Kathmandu  city  zone  to  Chhobar.  (3) A  big  proportion  of  the  augmented  Bagmati  flow  would  be  picked  up  at  Chobbar  for  diverting  it  into  the  Kulakhani  storage  reservoir.  As  a  result,  the  electricity  generation  of  the  existing  Kulekhani  No.1  and  Kulekhani  No.2  power  stations,  and  the  proposed  Kulakhani  No.3 Project could  be  tripled.  The  proposed  new plan  is  described hereinafter.   

Rationale  Behind  Melamchi- Langtang  Interconnection

The  concept  of  the  Melamchi-Langtang   interconnection  is  based  on  the  combination    of   independent  studies  of  various  projects  carried  out   at  different  time.  The  main  impetus  to  such  interconnected  project  is  provided  by  the  concurrence  of  the views  of  the  government   as  well  as  the  donors  to  acknowledge  the  need  to  implement  the  28  km  long  tunnel  to  deliver  Melamchi  water  to  Kathmandu  valley  to  meet  the  growing  demand  for  water supply  in  the  valley  until  2011.  There  after  the  water  of  the  Yangri  and  Larke  rivers  would  have  to  be  further  added.  There  are  two  serious  drawbacks  in   building  the  28  km  long  Melamchi  tunnel  project  exclusively  for  water  supply.  The  project  would   be  too  expensive   and  thus  the financial   burden  on   the  people  of  Kathmandu   would   be  too  heavy.  Each  customer  ultimately  might  have  to  pay  every   month  perhaps about   Rs. 5000  for  water  supply  unless  the  government  decides  to  pay  it  in the  form   of  subsidy.  Thus  an  overwhelming  majority  of  the  people  living  in  the valley  would  not  be  able  to  afford   to  bear  such  an extremely  high  cost  of  water  supply.

Langtang  River  Diversion

The   diversion     of  the  Langtang   river   for  water supply  to  Kathmandu  valley  is  not   a   new   concept.  Initially  it  was  thought  to  effect  diversion  from  the  catchments   area   instead  of  the  river.  A  study  of  such  diversion  was  made  by  GTZ  in  1977.  The  study  provides  the  following  information.

The  idea   to  augment  the  limited  water  resources of  the   Kathmandu   valley by  diversion of  water  from  the  Langtang / Gosaikund  massif  in  the North  was  first  mentioned  by  Peter  Aufschnaiter  in 1960.  In 1976 /77  the  project  was  studied  on  a  very  preliminary  level  by  Dr. Ing.  Cristian   Kleinert.   This  project, originally  not  listed   by  HMG  of  Nepal  under  the   projects  to  be  investigated  for  possible  cooperation  with  the  Germany   had  been  included  into  the  study  programme  on  the initiative  of  the   German  Government  Mission  itself  because  of  the  fascinating  concept  and  promising  objects.  The  Mission  report  points  out  that  at  that time the  high  cost  of  the  project  mainly  caused   by  difficult  access  and  transportation  would  not  make  it  viable  to  undertake  this  project  for  further  detailed  study.  Now  the  road  situation has  greatly  improved.

Multipurpose  Langtang  Development

The  concept  of  the  Langtang  project  solely  for  power  generation  was  developed  under  the  United  Nations  Development  Programme  supported  Gandak  Basin  Master  Plan  study.  This  project  can  be  easily  linked  with  the  Melamchi  project  tunnel.    The  interconnection   of   these  two  projects  could  open up  whole  new  vistas  for  the  most  cost effective   development  of  hydropower  in near  future. The  diversion  of  the  Melamchi- Langtang  flow  into  the  Kulekhani  could  be  regarded  as  one  of  such  possibilities. It  can  be  roughly  said  that  after  the  full  development  of  the Lantang-Melamchi-Kulekhani  interconnected  projects  it  could  be  possible  to  generate  about  2500  million  KWh  peaking  power at  a cost  of  about   2  US  Cents  per  KWh.  Three  hydropower  projects  each  operating  at  a  head  of  about  1000 m   or  more  with  a  total  installed  capacity  of  about  half a  million   KW  could  be  built  at  a  cost  of  about  US $  1000  per  KW.  After  the  completion  of  the  above  projects  the  Melamchi  tunnel  could  be  expected  to  run  in  full  capacity  of  about  15 cumecs  throughout  the  year  though the  Melamchi   river  alone  would   be  able  supply  only  about   1.5  cumec    or  even  less  in  dry  months  when  the  demand  for  water supply  in  the Kathmandu  valley  is  the  highest.  

Diversion  from  Kathmandu to Kulekhani

The  diversion  of  the  surplus  Melamchi  and  Langtang  waters   from  Kathmandu valley  to the  Kulekhani  reservoir  could  be  a  very  simple  and  at  the  same  time the most  cost  effective proposition  despite  the  fact  that  at  first  glance it  might  appear  to be a  highly  complicated  engineering  task.  Let  us take  a  hypothetical  case  that  we  are  going  to  draw   only  4  cumecs  water   somewhere  near  Chobar  out  of  the  combined  flow  of  the  Bagmati. Melamchi and  Langtang  rivers.  It  is explained  hereinafter  that  the  benefit  accruing  to  the NEA  could  be  as  high as  US $ 22.5  million  per  annum  by  investing  only  about  US $ 20  million  in  the  construction  of  the proposed  diversion structures.    

We  might  have  to  build  a  15 MW  pump  station   at  Chobar to  lift  4  cumecs  water  to  a  height  of  about  300  meters  which  might  be  equivalent  in  height  to  the  full  supply  level (FSL) of  the  Kulekhani  storage  reservoir. It  is  equally  possible  that  instead  of  one  big  pump station  we  might  need  several  small  pump  stations  with   a  total  capacity   of   about  15 MW  that  would  be  completely  dependant  on  topography.   A  15  km  long  waterway  might  be  needed  to  carry  the  water into  the  Kulekhani  storage  reservoir  out  of  it  the  length  of  the  tunnel  could  be  about  9  kilometers.  The  total  cost  of  such  diversion  could  be  about  US $  20 million

After  the  completion  of the  above  described   Langtang  diversion  into the Kulekhani  reservoir,  there  would  be  a  net  increase  of  about  250 GWh   firm  power  in  annual generation  of  the  Kulekhani  Nos  1,2&3  hydropower  stations  even  after  taking  into  consideration  the  energy  spent  on  pumping.  Thus  the  additional  generation  of  the  Kulekhani  hydropower stations  after  the   Langtang  diversion  would  be  two  times  greater  than  the  present  annual  generation  of  Kulekhani  No 1 Station. It  would  be  possible  to   increase  to  such  a  great  extent  the   electricity  generation  absolutely  without  any  additional  investment  in  civil  structures  and  electrical  equipments  of  the   Kulekhani  dam  and  hydropower  stations.

At  present  the NEA  is  paying  to  the  private developers  at an  average  rate  of  about  US  Cents  6  per  KWh.  Out  of  such purchase,  the firm  energy  is  only  about  50%  and  the  rest  is  secondary  energy.  The  purchase  rate  of  the  exclusively  firm  energy  could  be about   US Cents 9   per  KWh  if  it  is  presumed  that  3  KWh  secondary  energy  would   be  equivalent  1 KWh firm  energy  though  in  the  World  Bank  supported  Upper Karnali  Project  feasibility  study  the  seasonal  energy  has  been  valued  only  at  10%  of  the  firm  energy  based on the  expected  net  value of  such  energy  for  the thermal fuel  displacement.  Thus  even  a  small  scale  Langtang  diversion  into  the  Kulekhani   could   help  to  increase  the  annual  income  of  the  Kulekhani  hydropower  stations  by  a  wide  margin  of  US $  22.5  million  whereas  the  total   investment  in  the  pumping  system  to  deliver  the  water  into  the  Kulekhani  reservoir  could  be  only  about  US $ 20 million.

Threat To Langtang Melamchi Interconnection

Within  the past  decade  our  power  development  plans  have  been  thrown  into  a complete   disarray   by    foreign  developers  who were  virtually  given  free  hand  to  do  as  they  wish. The  task  of   regulatory  body  even  now  is  nothing  more than  a  mere  formality. The 60  MW  Khimti  hydropower, the  first  project  in  private  sector,  has  opened   a  Pandora's  box.  The  Khimti  project  had  disastrous  consequences  for  the  economy  of  the  Nepal  Electricity  Authority.  The  seasonal  energy   procured  from  the  Khimti  is  completely  wasted  though  NEA  is  made  to  pay   about US $   9  million  per  annum  for  such  seasonal  energy. Many  other  developers were also quick  to follow.  Some  of  them  are  already   building  hydropowers.  Few   have  recently  got permission  to  carry  out  detailed  study  but  they are not yet ready to start the construction  works. Mini Langtang project   appears  to  be   one  of  such  projects.      

We  would   have  to  sacrifice  the  big Langtang  Project if   it  is  decided   to  implement  this  mini  Langtang  project  because  they  are  mutually  exclusive.  The  mini  Langtang  project operating  at  a  head  of  about 200  meters   is  in  the  lowermost  reaches  of  the  Langtang  river.  The  water  supply to  the  mini  Langtang  project  would  have  to  be  completely  cut  off  to   divert     the  Langtang  river  into  the Melamchi.  So  all the  arrangements  made  with  the  private  developer  must  be annulled  before  it  is  too  late   to  save  the  big  Langtang  Projects  from  having  to  wage  legal  battle  later  on  against  the  private  developers 

In Conclusion

It  is  hoped  that  the  great  number  of  institutions  now  participating  in  the Bagmati  River  conservancy  works  and  the  Pashupatinath   Development  Trust  would  be  interested  to  explore  the  possibility  of  finding  engineering  solution  to  resolve  the  problems  arising  from  the present  worsening  situation  of  our  holy  Bagmati  River.

(Dr. Thapa writes on water resources)


|| Cover Story || Politics || Extortion || Health |View Point || Economy || Building Peace || Bullet In The Head |Tourism || Profile || Editor's Note || The Bottom Line || News Notes || Briefs || Quote Unquote || Off The Record || Letters || Opinion || Human Rights || Book Review || Past Issues ||


Send your feedback to the editor: spot@mail.com.np
2004   Mercantile Communications Pvt. Ltd. P.O. Box 876, Durbar Marg, Kathmandu, NEPAL. Tel : 977 1 4220 773, 4243 566 . Fax: 977 1 4225 407. Reproduction in any form is prohibited without prior permission. No part of the articles which appear in the internet version on SPOTLIGHT may be reproduced without the permission of Mercantile Communications Pvt. Ltd. For reprinting rights, please write to US. Send us your feedback: ABOUT US CONTACT US  HOME  
ADVERTISE WITH US

BACK TO THE TOP