![]() |
||
|
||
| OPINION |
Bagmati River
Conservation; A New Approach By Dr. AB Thapa At present the
Bagmati River has virtually turned into city drain. Residents
of the Kathmandu valley as well the large multitude
of peoples coming to Pashupatinath Temple each
day for worshipping from all over the world are
appalled at the miserable sight of the
holy Bagmati River. It can hardly be denied that
the water scarcity is the prime cause of
complete deterioration in condition of the
Bagmati River. Unfortunately until now we do not
have any satisfactory plan to resolve this
serious problem. We are pinning our hopes
on much publicized Melamchi Project, but
it is all eyewash: the Melamchi water will
not even reach Pashupatinath Temple area in
dry season. According to the Melamchi
Project report from 2011 onward the entire
Melamchi dry season flow would have to be
tapped to meet the growing demand for
water supply in the Kathmandu valley. Fortunately there is a good solution to resolve the Bagmati River conservancy problem. It would be possible to transform the Bagmati into a medium sized river that would be carrying a discharge of about 10 to 15 cumecs even in the driest month. Many of us might be astonished to learn that the proposed Bagmati flow augmentation program would not at all be a financial burden on residents of the Kathmandu valley. Full cost of the project could be recovered from the sale of the cheap hydro electricity. The generation cost of the electricity would be very low, as a result, it would even be possible to lower the present electricity tariff which might be among the highest in our region. It would
be possible to greatly enhance the feasibility
of the proposed Melamchi Project if this project
is coupled with the modified Langtang Project
which is not at all a very big project.
The whole plan would comprise of the
three steps. (1) Diversion of the Langtang
River into the Melamchi for generation of
cheap electricity. (2) The 28 km long proposed
Melamchi Project tunnel would deliver the combined
flows of the Langtang and the Melamchi
rivers into the Bagmati River near Sundarijal.
It would not be necessary to enlarge the
size of the Melamchi tunnel to deliver the
combined flow of the Melamchi and Langtang rivers.
The cross-sectional size of the proposed
Melamchi tunnel is too large It can easily
carry the combined flow of the Melamchi and the Langtang
rivers. The augmented Bagmati River would be
able to flush wastes held in suspension across
the Kathmandu city zone to Chhobar. (3) A
big proportion of the augmented Bagmati flow
would be picked up at Chobbar for
diverting it into the Kulakhani storage
reservoir. As a result, the electricity
generation of the existing Kulekhani No.1 and
Kulekhani No.2 power stations, and the proposed
Kulakhani No.3 Project could be tripled. The proposed
new plan is described hereinafter. Rationale
Behind Melamchi- Langtang Interconnection The
concept of the Melamchi-Langtang interconnection
is based on the combination of
independent studies of various projects carried
out at different time. The main impetus
to such interconnected project is provided by
the concurrence of the views of the
government as well as the donors to
acknowledge the need to implement the 28
km long tunnel to deliver Melamchi water
to Kathmandu valley to meet the growing
demand for water supply in the valley until
2011. There after the water of the Yangri
and Larke rivers would have to be further
added. There are two serious drawbacks in
building the 28 km long Melamchi tunnel
project exclusively for water supply. The
project would be too expensive and
thus the financial burden on the people
of Kathmandu would be too heavy.
Each customer ultimately might have to pay
every month perhaps about Rs. 5000 for
water supply unless the government decides to
pay it in the form of subsidy. Thus
an overwhelming majority of the people living
in the valley would not be able to
afford to bear such an extremely high cost
of water supply. Langtang
River Diversion The
diversion of the Langtang
river for water supply to Kathmandu valley
is not a new concept. Initially
it was thought to effect diversion from
the catchments area instead of the
river. A study of such diversion was made
by GTZ in 1977. The study provides the
following information. The
idea to augment the limited water resources
of the Kathmandu valley by diversion of
water from the Langtang / Gosaikund massif in the
North was first mentioned by Peter Aufschnaiter
in 1960. In 1976 /77 the project was studied on
a very preliminary level by Dr. Ing.
Cristian Kleinert. This project, originally not
listed by HMG of Nepal under the
projects to be investigated for possible
cooperation with the Germany had been
included into the study programme on the
initiative of the German Government Mission
itself because of the fascinating concept and
promising objects. The Mission report points out
that at that time the high cost of the
project mainly caused by difficult access
and transportation would not make it viable
to undertake this project for further detailed
study. Now the road situation has greatly improved. Multipurpose
Langtang Development The
concept of the Langtang project solely for
power generation was developed under the United
Nations Development Programme supported Gandak Basin
Master Plan study. This project can be
easily linked with the Melamchi project
tunnel. The interconnection of these
two projects could open up whole new vistas
for the most cost effective development of
hydropower in near future. The diversion of the
Melamchi- Langtang flow into the Kulekhani could
be regarded as one of such possibilities. It
can be roughly said that after the full
development of the Lantang-Melamchi-Kulekhani interconnected
projects it could be possible to generate
about 2500 million KWh peaking power at a cost
of about 2 US Cents per KWh. Three
hydropower projects each operating at a head
of about 1000 m or more with a total
installed capacity of about half a million
KW could be built at a cost of about
US $ 1000 per KW. After the completion of
the above projects the Melamchi tunnel could
be expected to run in full capacity of
about 15 cumecs throughout the year though the
Melamchi river alone would be able
supply only about 1.5 cumec or
even less in dry months when the demand
for water supply in the Kathmandu valley is the
highest. Diversion
from Kathmandu to Kulekhani The
diversion of the surplus Melamchi and Langtang
waters from Kathmandu valley to the Kulekhani
reservoir could be a very simple and at
the same time the most cost effective proposition
despite the fact that at first glance it
might appear to be a highly complicated engineering
task. Let us take a hypothetical case that
we are going to draw only 4 cumecs
water somewhere near Chobar out of the
combined flow of the Bagmati. Melamchi and Langtang
rivers. It is explained hereinafter that the
benefit accruing to the NEA could be as high
as US $ 22.5 million per annum by investing
only about US $ 20 million in the construction
of the proposed diversion structures. We might
have to build a 15 MW pump station
at Chobar to lift 4 cumecs water to a
height of about 300 meters which might be
equivalent in height to the full supply level
(FSL) of the Kulekhani storage reservoir. It is
equally possible that instead of one big pump
station we might need several small pump
stations with a total capacity of
about 15 MW that would be completely dependant
on topography. A 15 km long waterway
might be needed to carry the water into
the Kulekhani storage reservoir out of it
the length of the tunnel could be about
9 kilometers. The total cost of such
diversion could be about US $ 20 million After
the completion of the above described Langtang
diversion into the Kulekhani reservoir, there would be
a net increase of about 250 GWh firm
power in annual generation of the Kulekhani Nos
1,2&3 hydropower stations even after taking
into consideration the energy spent on pumping.
Thus the additional generation of the Kulekhani
hydropower stations after the Langtang diversion
would be two times greater than the
present annual generation of Kulekhani No 1 Station.
It would be possible to increase to
such a great extent the electricity
generation absolutely without any additional
investment in civil structures and electrical
equipments of the Kulekhani dam and
hydropower stations. At
present the NEA is paying to the private
developers at an average rate of about US
Cents 6 per KWh. Out of such purchase, the
firm energy is only about 50% and the
rest is secondary energy. The purchase rate
of the exclusively firm energy could be
about US Cents 9 per KWh if it is
presumed that 3 KWh secondary energy would
be equivalent 1 KWh firm energy though in the
World Bank supported Upper Karnali Project feasibility
study the seasonal energy has been valued
only at 10% of the firm energy based on
the expected net value of such energy for the
thermal fuel displacement. Thus even a small
scale Langtang diversion into the Kulekhani
could help to increase the annual income
of the Kulekhani hydropower stations by a
wide margin of US $ 22.5 million whereas
the total investment in the pumping system
to deliver the water into the Kulekhani
reservoir could be only about US $ 20 million. Threat To
Langtang Melamchi Interconnection Within the
past decade our power development plans have
been thrown into a complete disarray
by foreign developers who were virtually
given free hand to do as they wish. The
task of regulatory body even now is
nothing more than a mere formality. The 60 MW
Khimti hydropower, the first project in private
sector, has opened a Pandora's box. The
Khimti project had disastrous consequences for
the economy of the Nepal Electricity Authority.
The seasonal energy procured from the
Khimti is completely wasted though NEA is
made to pay about US $ 9 million per
annum for such seasonal energy. Many other developers
were also quick to follow. Some of them are
already building hydropowers. Few have
recently got permission to carry out detailed
study but they are not yet ready to start the construction works. Mini
Langtang project appears to be one of
such projects. We
would have to sacrifice the big Langtang Project
if it is decided to implement this
mini Langtang project because they are mutually
exclusive. The mini Langtang project operating at
a head of about 200 meters is in the
lowermost reaches of the Langtang river. The
water supply to the mini Langtang project would
have to be completely cut off to
divert the Langtang river into the
Melamchi. So all the arrangements made with the
private developer must be annulled before it is
too late to save the big Langtang
Projects from having to wage legal battle
later on against the private developers In
Conclusion It is
hoped that the great number of institutions
now participating in the Bagmati River conservancy
works and the Pashupatinath Development Trust
would be interested to explore the possibility
of finding engineering solution to resolve the
problems arising from the present worsening situation
of our holy Bagmati River. (Dr. Thapa
writes on water resources) |
|| Cover Story || Politics || Extortion || Health || View Point || Economy || Building Peace || Bullet In The Head || Tourism || Profile || Editor's Note || The Bottom Line || News Notes || Briefs || Quote Unquote || Off The Record || Letters || Opinion || Human Rights || Book Review || Past Issues || |
Send your feedback to the
editor: spot@mail.com.np |