http://www.nepalnews.com
spotlogo2.jpg (6318 bytes) VOL. 24, NO. 22, DEC 24 -  DEC 30  2004 ( PAUSH 09, 2061 B.S. )
OPINION

Dreadful Ordeal : Nepal Electricity Authority

By Dr. AB Thapa 

At present the Nepal Electricity Authority (NEA) is going through a dreadful ordeal. The NEA is now spending about 43% of its total revenue to purchase electricity from the private developers.  A brief  analysis presented hereinafter shows  that  the   electricity purchased  from  the  private developers  is   almost  entirely  wasted. As a result,  about  43% of  the total  NEA  revenue  is  uselessly  spent on purchase  of electricity from the private developers. Unfortunately  neither the NEA  nor the institutions like the World  Bank and  ADB  responsible  to monitor the  performance of the NEA are  seen  to  be concerned. 

The NEA Annual Report

Very   recently the  Nepal Electricity Authority (NEA)  has published  its   annual  report  2003/04  which  has  been  presented   in  full  detail  in  newspapers  such  as   “The Kathmandu Post”.   The  report   gives   a  very  gloomy  picture  of  the NEA.   It   is stated  in  the report  that  the NEA  registered   a  net loss  of  NRs. 1.78  billion  despite  the   fact  that  the  electricity  tariff  of  the NEA is   one of  the highest  in  our  region.  Most  of   the  NEA  revenue  went  towards  payments to  IPPs   (private developers).   About  43 percent of  the total revenue generated  was  utilized  in  purchasing  energy  from   IPP’s  and  about  30 percent  to  HMGN in  the   form of interest, principle and  royalty. The  cost  of   operation  and  maintenance  of  the  NEA operated   power  stations  is  about  9   percent.    The  NEA  is  perfectly  right in  pointing   accusing  finger  at  the  IPPs.  But  it  would   be  wrong  to  conclude  that  the  burden  of   interest  and  principles levied by  the HMGN on  external   loans  would  have even  slightly  contributed  to   worsening  of  the NEA’s  financial  situation.  The   fallacy  of  the  argument  about  the  excessive   burden  of  the  repayment  to  clear  the HMGN   loans  is  revealed  if  the  NEA  report  is    slightly scrutinized.  In  reality the present financial problems of  the NEA are  mainly  of  its  own  making.    The  NEA was  warned  of  the dire  consequences   of  careless  handling  of  the  IPP projects a  long   time ago.  Water  and Energy  Commission  had  even   circulated   a  proposal  suggesting  an  alternative   plan  that  would  have  been  eight  times   cheaper  by  comparison  with    the  Khimti,   Bhote-Kosi,  Indrawati  type  hydropower projects.

NEA Forced To Shut Down Its Power Stations

The NEA   might  be  shutting  down  partially  or  fully many of its  own hydropower  plants  for  a  considerable  length   of  period  each  year  particularly  in  wet   season  to  receive  electricity  purchased  from   the IPP owned  hydropower plants.  As  a  result,  the   NEA  owned  hydropower plants  are  operating  each   year  on an average  less than  3500 hours  whereas the IPP owned  hydropower plants are reported to be operating  6000 hours.

During the past financial year, according  to  the reporting of  the NEA, the electrical energy available  for  use  within  the NEA system totaled   2381.496 GWh.  This comprised of 1345.654 GWh  obtained  from   the NEA’s  own  hydropower plants  with  a  total   installed  capacity  of   389 MW, and  similarly   840.275 GWh  purchased  from  the IPPs owned  hydropower plants   with a  total installed  capacity  of  about  141 MW. These  data  explain  that  on  an  average  the   NEA  owned  hydropower plants  had been  running  for   only  3460   hours  in  a  year  whereas   the  IPP hydropower  plants  6000  hours.  As a  rule of thumb,  the hydropower  plants  with  a  small  storage   reservoir  to  regulate  the river flow on  a daily basis according  to the need for  water to  meet  the peak energy   demand  are  expected  to  run  on an  average   for  about  5000 hours or  slightly less  in  a year   unless  the  number  of  the  average  operating   hours  in  a year has  to  be  decided  from   some  other  specific  considerations.  In  case of   the hydropower plants  without  a  storage  pond  to   regulate river water on a daily basis,  the installed  capacity is decided  solely  on  the basis of  the availability  of   guaranteed  river flow  all the year round ( it  is  usually   90% probable discharge) since such plants would  not be  able  to   operate at  higher capacity  to  meet  the demand  for peaking energy  that  would have required  water supplies to the turbines in excess of  the  daily  available  guaranteed  river   water flow.  This scenario would  certainly change  and  we   would  have  to adopt  installed  capacity  in   excess of the  firm capacity if  we  are in  need  for   seasonal  energy.    

IPP Supplied Electricity Totally Wasted

What   would have happened  now if  we  did not have any of  the IPP owned hydropower plants?    The NEA owned  hydropower stations   alone would  have   generated  about  1940 GWh  per   annum  if  it is  presumed  that  they  operate   5000 hours  each year.  Similarly  the NEA owned  thermal plants with  a total  installed  capacity  of  about 56  MW   would  have  generated  about   150 GWh  if  it is  presumed  that  they  would  be operating on  an   average  3000 hours  each  year.  If  we  would   have purchased  about  300 GWh   electricity( perhaps about 75 MW in capacity)  from  India  ( in  the year 2002 it  was 238 GWh ),  the  total  electricity  available  for  use  would   have  been   about  2390  GWh  which  is   equal  to  the availability  of electricity  for  use   last  year  within  the NEA  system.  Similarly  the   total  capacity in the system  would have  been about  520 MW against  the  last year’s  peak  demand recorded at 515 MW.   It  implies  that  the  electricity  procured  from   the  IPP owned  hydropower  stations  is  now  almost   totally  wasted.  In  other  words  we  are   paying  almost  in  vain   Rs. 5.32  billion  (   or  43%  of  the NEA  revenue)   to  purchase   electricity  from  the  IPP  owned  hydropower   stations.

The NEA Could Soon Become Bankrupt

It  is   really frightening  to  note  that at  present  all   IPP hydropower plants ( with the exception of  the  Chilime Hydropower)   without  any storage  pond  to regulate  river water on  a daily basis  are perhaps  having  installed  capacity  three times  greater than  the  firm capacity ( in case of Khimti Project the installed capacity is 60 MW whereas the firm capacity is  only 18 MW).  As a result,  they  are  generating  enormously  large  surplus   seasonal energy , which is totally  wasted.   A  brief   analysis of  the  NEA  report  would  raise     fear  in  the mind  of  all  sensible    people  that  the  NEA  could   soon   become bankrupt  if  the  present  laissez-faire   hydropower  development  policy  is  allowed  to  be   continued The  followings  are  few  other concerns.  .

Who Checks  Electric Meters

The   yearly  average  operating  period  of   6000 hours   of  the  IPP owned  hydropower   stations  is   somewhat  too  high  because the installed  capacity  of   such hydropower plants  is  several  times  greater than   the  firm  capacity.  As mentioned earlier, the  installed   capacity  of  the  Khimti  Project  is  60 MW despite the  fact  that  the firm capacity  is  only  18 MW.   It  appears  all  the more  doubtful  since  some   of  the IPP  owned  hydropower  stations  have  to   be  completely  shut down  for  a long  period  each   year  to  divert  water  for  irrigation.  Moreover,    during  the wet seasons  the  Bhote-Kosi,  Indrawati   and Khimti  rivers would  be  heavily  laden with   sediments. As a  result,  the  hydropower stations  drawing   water  from  those  rivers would have  to  be  too   often  shut down  to  flush  out  the  sediments   that  would    to  a  considerable  extent   curtail  the  electricity  generation. 

It  would   not  be a great  surprise  if  the  meters to   register  the  supply  of  electricity  from  the   IPP hydropower stations  might  not  be  in  perfect order.  Needless  to  say  that  such  meters should   be  periodically  checked  and  certified.  Past   experience  has shown  the  NEA’s  poor  record    of  keeping  the  instrumentation  in  good   condition.  When  the  Kulekhani  High  Dam was  on   the  verge of  collapse  in  1980s  due  to   geological  problems,   at  that  time  it  was found  that  many  of  the  instruments  set up  during   the  construction  period   to  monitor  the   future  movements  of  the  dam  body  were   hardly  functioning. 

Future Load Shedding

The  IPP owned  hydropower plants are  not going  to be helpful to the NEA  in   future  also  to mitigate  crisis  of  power   shortage  when  the  demand  for  electricity   further  increases.  The  total  present  firm   capacity  of  all  the  IPP  owned hydropower   stations   might  be  only  about  60  MW   during  the  critical  dry  season  months  when   the  demand  for  electricity  is  the highest   despite  the fact  that  the present  total    installed  capacity  is  about  140 MW.  As a result,  the  real  total  generating capacity  in  the   system  would  be  only  about  505 MW( excluding procurement from India)  which  is  less  than  the maximum   peak  demand   recorded  at 515 MW  last year.  Thus   in  the coming  winter  reason  load  shedding    would  be inevitable  if  electricity is not  imported   from  India. 

Can We Export Seasonal Energy?

It is   quite unfortunate that some of our friends  in  the Government  are   placing  high  hopes on  export  of  seasonal  energy   to  India  to promote  IPP projects.  We should  beware   of  such  misleading  perception.  Our  own study  of   the  Upper Karnali Project  carried  out  with  the   assistance  of  the World  Bank  explains  that  the value  of  our  seasonal  energy  to  Indian system  to   displace  temporarily  fossil fuel  could  be only about   10%  of  the  value  of  the  firm  energy   whereas  the  cost of  energy  transmission  to   India  ( wheeling charge) could  be  somewhere around  15%   of  the total  value of  the  mostly  firm  energy   based  on  the  recent  agreements  reached  between   various  states  of  India.  Thus  we would  be   incurring  a loss  by exporting  seasonal  energy  if   special  circumstances  did  not warrant India  to  buy   such  energy at  a fairly  high price.

In Conclusion

It  is   often  said  that  many  developing  countries  are   unable  to  bolster  up   the  economy   at   a  reasonable  pace  not  for  want of  natural   resources  or  capital.  They  are  progressing    very  slowly  because  their  policy  makers   and  planners    posses  neither  a  clear   vision  of  their  country’s  development   perspectives  nor  the ability  and  true  dedication   to  lead  the  country  in  the  path  to   victory  over  underdevelopment  and   backwardness.   Certainly  in  this  matter Nepal  is  not  an   exception.  Our  country  is  also  suffering  from   the  same  type  of  ailment.  Planners  and   policy  makers  in  our  country  need  to  have   clear  vision and  true  dedication  to  their   works. 

At present Nepal Electricity Authority is facing a terrible financial crisis. The NEA had to resort   to  repeated  hiking  of  the electricity tariff  to cover its losses.  Unfortunately  nobody is seen  to  be truly   interested  to  diagnosis  the  ailment of  the NEA.   It is hoped  that  the PDF  loan  going to be provided  to Nepal by the World Bank would not be spent  to  further worsen the   financial situation of the NEA  by  investing  on projects like the Khimti, Bhote-Kosi, Indrawati etc. 

(Dr. Thapa writes on water resources)


|| Cover Story || Nepal HDR 2004 || Bhutanese Refugess || Icons 2004 || Encounter || Security Personnel ||
||
Why Study abroad? || Is Constitution the Culprit ? || Human Cost || Forum || Editor's Note || The Bottom Line ||
|| News Notes || Briefs || Quote Unquote || Off The Record || Letters || Opinion ||
Book Review  || Past Issues ||


Send your feedback to the editor: spot@mail.com.np
2004   Mercantile Communications Pvt. Ltd. P.O. Box 876, Durbar Marg, Kathmandu, NEPAL. Tel : 977 1 4220 773, 4243 566 . Fax: 977 1 4259429. Reproduction in any form is prohibited without prior permission. No part of the articles which appear in the internet version on SPOTLIGHT may be reproduced without the permission of Mercantile Communications Pvt. Ltd. For reprinting rights, please write to US. Send us your feedback: ABOUT US CONTACT US  HOME  
ADVERTISE WITH US

BACK TO THE TOP