![]() |
||
|
||
| OPINION |
Dreadful Ordeal : Nepal Electricity Authority By Dr. AB
Thapa At present the
Nepal Electricity Authority (NEA) is going through a dreadful ordeal. The NEA is now
spending about 43% of its total revenue to purchase electricity from the private
developers. A brief analysis presented hereinafter shows that the
electricity purchased from the private developers is
almost entirely wasted. As a result, about 43% of the
total NEA revenue is uselessly spent on purchase of
electricity from the private developers. Unfortunately neither the NEA nor the
institutions like the World Bank and ADB responsible to monitor
the performance of the NEA are seen to be concerned. The NEA
Annual Report Very
recently the Nepal Electricity Authority (NEA) has published its
annual report 2003/04 which has been presented
in full detail in newspapers such as The
Kathmandu Post. The report gives a
very gloomy picture of the NEA. It is
stated in the report that the NEA registered a
net loss of NRs. 1.78 billion despite the fact
that the electricity tariff of the NEA is one
of the highest in our region. Most of the
NEA revenue went towards payments to IPPs (private
developers). About 43 percent of the total revenue generated
was utilized in purchasing energy from
IPPs and about 30 percent to HMGN in the
form of interest, principle and royalty. The cost of
operation and maintenance of the NEA operated
power stations is about 9 percent.
The NEA is perfectly right in pointing accusing
finger at the IPPs. But it would be
wrong to conclude that the burden of
interest and principles levied by the HMGN on external
loans would have even slightly contributed to
worsening of the NEAs financial situation. The
fallacy of the argument about the excessive
burden of the repayment to clear the HMGN
loans is revealed if the NEA report is
slightly scrutinized. In reality the present financial problems
of the NEA are mainly of its own making.
The NEA was warned of the dire consequences of
careless handling of the IPP projects a long time
ago. Water and Energy Commission had even
circulated a proposal suggesting an alternative
plan that would have been eight times
cheaper by comparison with the Khimti,
Bhote-Kosi, Indrawati type hydropower projects. NEA
Forced To Shut Down Its Power Stations The NEA
might be shutting down partially or fully many of
its own hydropower plants for a considerable length
of period each year particularly in wet
season to receive electricity purchased from the IPP
owned hydropower plants. As a result, the NEA
owned hydropower plants are operating each year on an
average less than 3500 hours whereas the IPP owned hydropower
plants are reported to be operating 6000 hours. During the past
financial year, according to the reporting of the NEA, the electrical
energy available for use within the NEA system totaled
2381.496 GWh. This comprised of 1345.654 GWh obtained from the
NEAs own hydropower plants with a total
installed capacity of 389 MW, and similarly 840.275
GWh purchased from the IPPs owned hydropower plants with
a total installed capacity of about 141 MW. These
data explain that on an average the NEA
owned hydropower plants had been running for only
3460 hours in a year whereas the IPP
hydropower plants 6000 hours. As a rule of thumb, the
hydropower plants with a small storage
reservoir to regulate the river flow on a daily basis
according to the need for water to meet the peak energy
demand are expected to run on an average
for about 5000 hours or slightly less in a year
unless the number of the average operating
hours in a year has to be decided from
some other specific considerations. In case of the
hydropower plants without a storage pond to regulate
river water on a daily basis, the installed capacity is decided
solely on the basis of the availability of guaranteed
river flow all the year round ( it is usually 90% probable
discharge) since such plants would not be able to operate
at higher capacity to meet the demand for peaking
energy that would have required water supplies to the turbines in excess
of the daily available guaranteed river water
flow. This scenario would certainly change and we
would have to adopt installed capacity in excess of
the firm capacity if we are in need for
seasonal energy. IPP
Supplied Electricity Totally Wasted What
would have happened now if we did not have any of the IPP owned
hydropower plants? The NEA owned hydropower stations alone
would have generated about 1940 GWh per
annum if it is presumed that they operate 5000
hours each year. Similarly the NEA owned thermal plants with
a total installed capacity of about 56 MW would
have generated about 150 GWh if it is
presumed that they would be operating on an
average 3000 hours each year. If we would have
purchased about 300 GWh electricity( perhaps about 75 MW in
capacity) from India ( in the year 2002 it was 238 GWh
), the total electricity available for use would
have been about 2390 GWh which is
equal to the availability of electricity for use
last year within the NEA system. Similarly the
total capacity in the system would have been about 520 MW
against the last years peak demand recorded at 515 MW.
It implies that the electricity procured from
the IPP owned hydropower stations is now almost
totally wasted. In other words we are
paying almost in vain Rs. 5.32 billion (
or 43% of the NEA revenue) to purchase
electricity from the IPP owned hydropower stations. The NEA
Could Soon Become Bankrupt It is
really frightening to note that at present all
IPP hydropower plants ( with the exception of the Chilime Hydropower)
without any storage pond to regulate river water on a daily
basis are perhaps having installed capacity three
times greater than the firm capacity ( in case of Khimti Project the
installed capacity is 60 MW whereas the firm capacity is only 18 MW). As a
result, they are generating enormously large surplus
seasonal energy , which is totally wasted. A brief
analysis of the NEA report would raise
fear in the mind of all sensible people
that the NEA could soon become bankrupt
if the present laissez-faire hydropower development
policy is allowed to be continued The
followings are few other concerns. . Who
Checks Electric Meters The
yearly average operating period of 6000 hours
of the IPP owned hydropower stations is
somewhat too high because the installed capacity of
such hydropower plants is several times greater than
the firm capacity. As mentioned earlier, the installed
capacity of the Khimti Project is 60 MW despite
the fact that the firm capacity is only 18 MW.
It appears all the more doubtful since some
of the IPP owned hydropower stations have to
be completely shut down for a long period each
year to divert water for irrigation. Moreover,
during the wet seasons the Bhote-Kosi, Indrawati
and Khimti rivers would be heavily laden with
sediments. As a result, the hydropower stations drawing
water from those rivers would have to be too
often shut down to flush out the sediments
that would to a considerable extent
curtail the electricity generation. It would
not be a great surprise if the meters to
register the supply of electricity from the IPP
hydropower stations might not be in perfect order.
Needless to say that such meters should be
periodically checked and certified. Past experience
has shown the NEAs poor record of
keeping the instrumentation in good condition.
When the Kulekhani High Dam was on the verge
of collapse in 1980s due to geological
problems, at that time it was found that
many of the instruments set up during the
construction period to monitor the future
movements of the dam body were hardly
functioning. Future
Load Shedding The IPP
owned hydropower plants are not going to be helpful to the NEA in
future also to mitigate crisis of power
shortage when the demand for electricity
further increases. The total present firm
capacity of all the IPP owned hydropower
stations might be only about 60 MW
during the critical dry season months when
the demand for electricity is the highest
despite the fact that the present total
installed capacity is about 140 MW. As a result,
the real total generating capacity in the
system would be only about 505 MW( excluding procurement
from India) which is less than the maximum peak
demand recorded at 515 MW last year. Thus in
the coming winter reason load shedding would be
inevitable if electricity is not imported from India.
Can We
Export Seasonal Energy? It is
quite unfortunate that some of our friends in the Government are
placing high hopes on export of seasonal energy
to India to promote IPP projects. We should beware
of such misleading perception. Our own study of
the Upper Karnali Project carried out with the
assistance of the World Bank explains that the
value of our seasonal energy to Indian system to
displace temporarily fossil fuel could be only about
10% of the value of the firm energy
whereas the cost of energy transmission to
India ( wheeling charge) could be somewhere around 15%
of the total value of the mostly firm energy
based on the recent agreements reached between
various states of India. Thus we would be
incurring a loss by exporting seasonal energy if
special circumstances did not warrant India to buy
such energy at a fairly high price. In
Conclusion It is
often said that many developing countries are
unable to bolster up the economy at
a reasonable pace not for want of natural
resources or capital. They are progressing
very slowly because their policy makers
and planners posses neither a clear
vision of their countrys development
perspectives nor the ability and true dedication
to lead the country in the path to
victory over underdevelopment and backwardness.
Certainly in this matter Nepal is not an
exception. Our country is also suffering from
the same type of ailment. Planners and
policy makers in our country need to have
clear vision and true dedication to their
works. At present
Nepal Electricity Authority is facing a terrible financial crisis. The NEA had to resort
to repeated hiking of the electricity tariff to cover
its losses. Unfortunately nobody is seen to be truly
interested to diagnosis the ailment of the NEA. It is
hoped that the PDF loan going to be provided to Nepal by the
World Bank would not be spent to further worsen the financial situation
of the NEA by investing on projects like the Khimti, Bhote-Kosi,
Indrawati etc. (Dr. Thapa
writes on water resources) |
|| Cover
Story || Nepal HDR 2004
|| Bhutanese Refugess || Icons
2004 || Encounter || Security
Personnel || |
Send your feedback to the
editor: spot@mail.com.np |