![]() |
||
|
||
| OPINION |
WHO CHECKED DESIGN? West Seti Dam Disaster Dr. AB Thapa Nepal might be heading for a big dam
disaster. Our government is on the verge of granting permission to
a private developer to build 195 m high concrete
faced rock filled dam (CFRD) which would be the highest in the world
among this type of dams built so far. Needless to say that it is cheap
to build this type of dam. Unfortunately our government has
not cared to constitute a panel of
internationally known competent experts to verify the
reliability of the design of the proposed dam. It is very
clear that tens of thousands of people would be
killed if the West Seti Dam collapsed due to
faulty design. Vast area of lands in Nepal and India
would be laid waste with sand deposits. Those of us involved
in the process of granting permission to the private developer to
build the West Seti Dam without verifying the
technical design should take this matter very
seriously before it is too late. This brief article is
published to draw the attention of the National
Planning Commission and its Honorable Vice-Chairman and Members,
Ministry of Water Resources, Ministry of Environment etc. to
realize the gravity of the situation. Certainly institutions like the
ICIMOD set up to resolve mountain development problems can not
distance itself from West Seti Dam Disaster issue that
could trigger unprecedented water induced catastrophe
in our whole region. German Government Ruled Out CFRD It has been proposed
to build a 195 m high embankment
type dam across the West Seti river. It
need not be explained that the embankment
type of dam with impervious earthen core is the
best suited for the proposed site. However,
good deposits of suitable materials for
impervious core could not be found nearby.
It led to find an alternative
to the impervious earthen core embankment
dam. So it was decided to build a
concrete face rockfill dam ( CFRD ). Needless to say
that such dam even according to the
study report of the private developer is the
least expensive. Now the question arises whether
it is safe to build this type of
dam in Nepal. Almost the same type
of problem was encountered about 20
years earlier in 1970s while planning the
Kankai High Dam by the German consulting firm
SALZGITTER. CFRD was one of the alternatives.
However, the scale of the problem
at that time was far smaller. By comparison
with the West Seti dam 195 meters in
height, the Kankai high dam is
just 85 meters in height. Nevertheless
the German Government took this matter very
seriously. Despite the fact that there
are countless good geotechnical experts in
the Germany itself, German Government
constituted a small panel under a
renowned French professor to review
the study report and to make appropriate
recommendation. Only after such through recheck
it was decided to adopt the embankment type
dam with an asphaltic concrete facing. There
were already several dams of this type
close to the proposed Kankai dam in
height in good operation all across the
world and it was the strongest
justification in support of the decision to
select this type of dam with an asphaltic
concrete facing. Unfortunately it might not
be possible to justify in a similar way
the proposed dam type in respect of the
West Seti dam. Why West Seti Dam
Could Be Unsafe? The West Seti Project will
have a 195-m high concrete face rockfill dam ( CFRD ). This
type of dams are found to be very competitive in cost but until
recent time they were considered risky for heights
above 150 meters. This type of dam
could have also been considered as one of
the alternatives in selection of the high
dam for the Kankai Project. The French
expert called in to advise on Kankai
dam appears to have dissuaded the German
study team from considering the CFRD as a
viable option. It was considered that it
could be unsafe to build the CFRD. So
finally at the end an embankment type
dam with an asphaltic concrete face was
selected. The CFRD is very
sensitive to settlement and deformation of the rock-fill
supporting the upstream face. These deformations produce
movements of the concrete slab joints by opening them
and if the movements exceed certain limits
then the resulting leakage is difficult to
control. The deformations of CFRD for dynamic
loading are even more difficult to evaluate.
In the Michigan Convention of ASCE in 1985 on CFRDs
papers were presented to establish Earthquake Severity Index
(ESI) with relative vertical settlement. In the ICOLD
meeting of 1988 it was suggested that future research
should be focused to correlate ESI and the
relative settlement as function of yield acceleration. There is no
Precedent Needless to say that
there is a need for great caution
in adopting very high CFRD. According to
J. Barry Cooks, Consultant USA ( Development in
High CFRDs, Hydropower & Dams, Issue Four 1997), this
type of dams are of empirical design and
based on precedent design and experience.
Unfortunately only very recently relatively high CFRDs
have been introduced. The proposed developer of
the West Seti Project has cited as precedent in their
report two CFRDs close to the West Seti
dam in height. It is claimed that
they are already in good service. They are
the Tiensingquiao of China with a height of 180
meters and Aguamilpa of Mexico with a height of 185.5
meters. Unfortunately both these CFRDs can not be
satisfactory example to justify the selection
of CFRD for the West Seti Project.
The Tiensigquiao dam of China might be
still under construction. According to the
original schedule the dam was expected to
be completed towards the May of 1999. So
nobody might be yet knowing how that dam
would be going to perform. The Aguamilpa
reservoir was first filled in August 1993.
Since then two abnormal peak seepage values have been
observed. These events were of great concern, and several
hypothesis were made to explain this behaviour although
none has been satisfactory. Now underwater
inspections are in progress to try to identify any
factor, which could explain the observed behaviour. There are not any
other examples in the world of CFRDs in service with
heights close to 195 meters. It is a fact
that very high CFRDs are yet to be
tested in practice. So a great deal of
caution is required to adopt this type of
dam. Let us not take the risk of
unnecessarily endangering the life and property
of innumerable people by recklessly
deciding to implement the West Seti Project.
There are several such instances when a
country had to pay dearly for the
unpardonable mistakes committed by the decision
makers. Dam Failures Insensitivity to advise
from outsiders could have terrible consequences.
A case in point could be the Malpasset dam near
Frejus in Southern France. It is reported
that the decision makers were cautioned
in time. They were told that the dam
site was not suitable so it was
recommended that the dam be built elsewhere.
However, for reasons of engineering convenience, the
advice was disregarded. The dam failed on
2nd December, 1959, causing death of a
large number of people. Construction of the high
dam without full study of the environs
led to the catastrophe of the Vaiont Dam
in Italy. The Vaiont Dam is 261 meters high and
the volume of the water contained in its reservoir is
150 million cubic meters ( the volume of
the West Seti reservoir would be about
1500 million cubic meters). In September, 1963 the
reservoir level reached a height of 180 meters,
and an earth movement started along the slope of
Mont Toc. That movement accelerated in October and
caused a landslide which gave rise to a
giant wave that flooded the valley beneath, wiping
out several villages and killing more than 2,000
people. Shoddy workmanship and poor
quality of materials are often the prime
cause of dam failures. The failure of St. Francis
dam in California has been attributed to
faulty foundations. Design errors were apparently
largely responsible for the collapse of
the Teton dam. In our own region
over-topping occurred with the Machau II dam in
India in 1979 and caused the death of 1,500
people downstream. In this case, the malfunctioning
of equipment contributed to the failure, as
the spillway gates could not be opened in
time. The failure of spillways to function properly
also led to the near failure of the 140 m high
Tarbela dam in Pakistan in 1975-6. It is
reported that in this case design errors and
possible poor construction materials were also
involved. Nepals laissez-faire
hydropower development policy could have
adverse effect on dam safety. It is
difficult to visualize how we can be
assured that the private developers would
be sincerely interested in maintaining
the high standard of workmanship and
superior quality of materials which are
fundamental prerequisite for dam safety that
would invariably lead to higher cost.
What is the guarantee that the private
developers would not be tempted to cut a
lot of corners in order to make
hefty profit that could be disastrous in
long run. In Conclusion At present anybody
even with the slightest knowledge of water
resources would be eagerly waiting to
get befitting answers to the problems
briefly described in this short paper
from the management of the Water Resources
Ministry. We all should remember that what
is now at issue is the safety of
life and property of tens of thousands of
people living in the Western Nepal. (Dr. Thapa writes on water resources) |
|| Cover
Story || Supreme Court || National Reconciliation || Health Issues In Dhading || Interview || Architect
Award || |
Send your feedback to the
editor: spot@mail.com.np |