http://www.nepalnews.com
spotlogo2.jpg (6318 bytes) VOL. 23, NO. 48, JUNE 18 -  JUNE 24  2004 ( ASHADH 04, 2061 B.S. )
OPINION

DAM   DISASTER:  Kulekhani And West Seti

By Dr. A.B. Thapa

In 1970s,   the  construction  of   the  Kulekhani  High   Dam  Project  was  about  to  begin.  I  had   horrible  suspicion  that  the  geology  of  the   Kulekhani  dam  site area  could  be  problematic.  I   published  an  article about  that  in  the   newspaper “ The  Rising  Nepal”.  Some  other local   and  foreign  newspapers   also  carried  partially   the content  of  my  article shortly  thereafter.  That   news  was  very  seriously  taken  up  by  the   World  Bank  and  the government.  Much  later  on,   I  learnt  that I  was  going to  be  charged   with  criticizing  the government  decision   The   case was  dropped,  when few  of  my  colleagues   stepped  in  to  plead  on my  behalf.  It  is   said   that  extra  concrete  grouting  works   and   other  measures  were  taken   up  to    protect  the  riverbed  and  the  terraces   just  adjacent   to  the  dam  to  ensure   safety.   Despite  such  limited   measures,   few  years  after  the  completion  of  the Kulekhani   dam   news   came  out  of  the  blue   that  very  wide  cracks  have  already  developed    over  an  wide  area  adjacent   to  the    intake  structures  on  the  right  bank.  It   appeared  that  the  Kulekhani  dam  was  on   the  verge  of  collapse. 

An   Ironic Twist To The  Story

The   misgivings  I  had  about  the   poor   geological  conditions  turned  into  the   gravest   reality.  At that time,  I  was  heading  the   monitoring  section of  the  Water Resources  Ministry.   Dr. John Cooper and  Mr. Deepak Gyawali  from  WECS  had   visited the  Kulekhani  dam site  to  spend  the   weekend.  They were  shocked  to  find  that  the   Kulekhani  dam  was  at  the risk of  being washed   away.  I  got  the full  reporting  from  them    It  was  feared  that  at  any  time  in   near future a   very  big  portion  of  the   right  bank  terrace  along  with  the  intake   structure  could  plunge  into  the  reservoir   setting  in  motion   a  huge  big  mass   of   the  reservoir  water  to  overtop  the   dam.  In  a  similar  type  of  Vajont  dam   incident  in  Italy,  the  loss  of  life  was   significant    even  though   the   dam   was  left  standing   after  the  overtopping   because   it  was  a  concrete  dam.  However,   the  whole  project  was  rendered  useless    after  that  incident.  In  case  of   the   Kulekhani  dam  made  of  earthen  core  the   whole  dam  body  would   have  been  completely   washed  away  after  the   overtopping. 

I  had   to  play  the lead role on  behalf of  the ministry in expediting  the  civil  works to  save  the  Kulekhani   dam   Leading  experts   from  the  USA,   Australia  and  Japan   were  called   in    for  consultation  shortly  thereafter.   On   their   recommendations   works  such   as    the   clearing  of   large  volume  of    weathered   materials,  anchor  bolting   of   huge   masses    of  rocks   to   prevent   sliding  into  the  reservoir,    provision  of  underground  drainage  system    were  carried   out.    Nepal  was   guided  all  along   by  the  advice   of    the   donor  agency.   Their  timely   assistance   helped   to  preclude the  possibility   of  Nepal  being  hit  by   a   big    disaster. 

Dam   Failures

Insensitivity   to   advise  from  outsiders  could  have   terrible  consequences.  A case in  point  could  be the   Malpasset  dam  near  Frejus  in Southern  France.    It  is  reported  that   the  decision   makers  were  cautioned  in time.   They  were   told  that  the  dam  site  was  not  suitable   so  it  was  recommended  that  the  dam  be   built  elsewhere.  However, for  reasons  of  engineering   convenience,  the  advice  was  disregarded.   The   dam  failed on  2nd  December, 1959,  causing  death   of   a  large  number  of  people.

Construction   of  the  high  dam  without   full  study   of  the  environs  led  to  the  catastrophe  of   the Vajont  Dam  in  Italy.  The Vajont Dam  is  261 meters  high  and  the volume  of  the  water contained in its  reservoir is  150  million  cubic  meters (  the   volume  of  the  West  Seti  reservoir  would   be  about  1500  million  cubic  meters). In September, 1963  the  reservoir  level  reached a  height of  180   meters,  and  an  earth movement  started  along  the   slope of  Mont Toc.  That  movement accelerated in  October   and  caused  a  landslide  which  gave  rise  to a  giant  wave  that  flooded the  valley beneath,  wiping   out  several  villages  and  killing more  than   2,000 people.

Shoddy    workmanship  and  poor  quality  of  materials   are   often  the  prime  cause  of  dam   failures.  The failure of  St. Francis  dam  in   California  has  been  attributed  to  faulty   foundations.  Design  errors  were  apparently    largely  responsible  for  the  collapse  of   the  Teton  dam.  In our own region,  ‘over-topping’ occurred with  the Machau  II  dam  in  India in 1979  and   caused  the  death  of  1,500 people  downstream.  In   this  case,  the  malfunctioning  of  equipment   contributed  to  the  failure,  as  the  spillway   gates  could  not  be  opened  in time.  The   failure of  spillways  to  function  properly  also   led  to  the near failure of  the  140 m  high   Tarbela  dam in  Pakistan  in 1975-6.  It  is   reported  that  in  this  case design errors  and   possible  poor  construction  materials  were   also   involved.

Nepal’s   laissez-faire   hydropower  development   policy   could   have  adverse   effect on  dam  safety.    It  is  difficult  to  visualize  how  we   can  be  assured   that  the  private   developers  would   be  sincerely   interested    in  maintaining   the  high   standard  of   workmanship  and  superior  quality  of  materials    which  are  fundamental  prerequisite   for   dam  safety  that  would   invariably   lead   to  higher  cost.  What  is  the  guarantee    that  the private  developers  would  not  be   tempted  to  cut  a  lot  of  corners  in   order  to  make   hefty  profit  that  could   be  disastrous   in  long  run.

West   Seti  Dam  Safety

Now  talks   are going  on  about  the  direct  involvement  of   the  private  developer  in  the  implementation  of   the  mammoth  West  Seti storage  dam  project     Everybody    is  at  a  great  loss   to  understand   who would   be  actually   responsible  to  ensure  that  this  highly   sensitive  project  would  be  planned  and   implemented   fully  complying  the  well    established  internationally  accepted  engineering   practices.  

The  West   Seti  dam  project  appears   to  be    ridden  with  very  serious  technical  problems   that  concern  the  safety   of  its  most   important  structure, the  high  dam  itself.  The   WECS  had   few  years  back  sent  its   opinion  to  the  Water Resources  Ministry  stating   that  the  type  of  the   high   dam    proposed  for  the  West  Seti  by     the  private  developer  could   be   risky.   Some  of  the  evidences  put  forward   by  the  developers  to  justify  their  selection   do  not  appear  to  tally  with   the   information  contained   in  the   recently   published  scientific  documents.  So  it  was   suggested  to  constitute   a panel   of  few    renowned   international  experts   recognized   to  be  the  authority  on  their  respective   discipline  to  seek  their  opinion.   Any   further  action  in  the  direction  of   taking   the  decision   to  award   the  project   to  the  private  developer  should  be  deferred    until  the  panel  gives  its  absolutely   positive  opinion.    It  is  not  known    who   had  approved   the   technical    design  of  the  West  Seti  project   on   behalf  of  the  government  to  vouch  for  the   correctness.   Unfortunately,   the  developers  were   allowed  to  go  ahead  to  find  buyers  for   the  electricity. Every  sensible  man  will  agree   that  the  West  Seti  dam  should  be    completely  safe.   The  incident  of  the   Kulekhani  High  Dam  should  not  be  allowed   to  be  once  more  repeated.  At  that  time   the  Kulekhani  dam  could  be  saved   which   was  on  the  verge  of  collapse   resulting   into  one  of  the  biggest  man      made  disasters in  the  world     In   case  of the   West  Seti   reservoir  the  magnitude   of  such  disaster   would  be  far  greater  because  the  volume   of   the  West  Seti  reservoir   might    be  about   15   times   greater   than  the  volume  of   the  Kulekhani   reservoir.

Why   West  Seti  Dam  Could  Be  Unsafe?

The  West Seti Project  will  have  a  195-m high  concrete face   rockfill dam ( CFRD ). This type  of  dams are found to be very competitive in  cost but  until recent time  they  were   considered  risky  for  heights  above  150  meters.   This  type  of  dam   could  have  also   been  considered  as  one  of  the  alternatives   in  selection  of  the  high  dam  for  the   Kankai Project.   The  French  expert  called  in   to  advise  on   Kankai  dam  appears  to   have  dissuaded  the  German  study  team  from   considering  the  CFRD  as  a  viable  option.   It  was   considered  that  it  could  be   unsafe  to  build  the  CFRDs.  So  finally  at   the   end  an  embankment  type  dam  with   an  asphaltic  concrete  face  was  selected.

The  CFRD   is  very sensitive to  settlement and  deformation  of   the  rock-fill  supporting  the  upstream face.  These deformations produce  movements  of  the  concrete slab joints   by  opening  them and  if  the  movements  exceed   certain  limits  then  the  resulting leakage  is   difficult  to  control.   The  deformations  of CFRD   for dynamic  loading  are  even  more  difficult  to   evaluate.  In  the  Michigan Convention   of  ASCE in   1985  on CFRDs  papers were presented to  establish  Earthquake   Severity  Index (ESI) with  relative  vertical settlement. In   the  ICOLD  meeting of   1988 it  was suggested  that   future  research should  be  focused  to  correlate   ESI and  the  relative settlement  as  function  of   yield acceleration.

There   is  no  Precedent

Needless   to  say  that  there  is  a  need   for    great  caution  in  adopting   very  high   CFRD.  According  to J. Barry  Cooks,  Consultant  USA    (   Development in High CFRDs,  Hydropower  &   Dams, Issue Four 1997),  this  type  of  dams  are of    empirical  design  and  based  on  precedent   design  and  experience.  Unfortunately,  only  very   recently  relatively  high  CFRDs have  been  introduced.

The   proposed  developer of  the  West  Seti Project  has   cited as precedent in  their report  two  CFRDs  close  to   the  West  Seti  dam  in  height.  It  is   claimed  that    they  are  already  in   good  service.  They  are the  Tiensingquiao of  China   with  a  height  of  180 meters and Aguamilpa  of   Mexico with  a  height of  185.5 meters.  Unfortunately,   both  these CFRDs can  not  be  satisfactory  example   to  justify  the  selection  of  CFRD  for    the  West  Seti  Project.  The  Tiensigquiao   dam  of  China  might  be  still  under   construction.  According  to  the  original  schedule   the  dam  was  expected  to  be  completed   towards  the  May  of  1999.  So  nobody  might   be  yet  knowing how  that  dam  would  be   going  to perform.  The  Aguamilpa   reservoir  was   first  filled  in August  1993.  Since  then two   abnormal peak seepage  values  have  been  observed. These   events  were of  great  concern, and several  hypothesis   were  made  to explain this  behaviour  although none has   been  satisfactory.  Now  underwater   inspections   are in  progress  to  try to identify  any  factor,   which  could  explain  the  observed  behaviour.

There  are   not  any  other  examples in the world  of CFRDs  in service  with  heights  close  to 195  meters.  It  is   a  fact  that  very  high  CFRDs  are  yet   to  be  tested  in  practice.  So  a  great   deal  of  caution is  required   to  adopt  this type  of  dam.  Let  us  not  take  the  risk   of   unnecessarily  endangering   the  life  and   property  of   innumerable  people  by    recklessly  deciding  to  implement  the  West   Seti  Project. 

In   Conclusion

Nepal’s   laissez-faire   hydropower  development   policy   could   have  adverse   effect on  dam  safety.    Until now,  our  government’s  performance  in   handling  private  developers  of  hydropower  projects   has  been  extremely  shocking.   Government   endorsed  whatever  the  private  developers  proposed.   There  is  nobody  from  the  government  side   to  check  the  works  of  the  private   developers  at  the  site.  As  a  result,  in   case  of  the  Bhotekosi  Project   the   concerned  Department  and  the Ministry  came  to   know  that   the  installed  capacity  of  that   hydropower  project   had  been   raised  from   35 MW  to  45 MW  completely  defying  the  power   purchase  agreement  only  after the  completion  of   the construction  works.  Government  learnt  about  it   only  after  a  claimed  was  lodged  by  the   private developer  with  the  government   to  compel   the  NEA  to  buy   extra  power  to  be generated  entirely  during  the  monsoon  season  which   is  going  to  be  totally  wasted. 

It  is   difficult  to  visualize  how  we  can  be   assured   that  the  private  developers  would    be  sincerely   interested   in  maintaining    the  high   standard  of  workmanship  and   superior  quality  of  materials   which  are   fundamental  prerequisite   for  dam  safety  that   would   invariably   lead  to  higher  cost.   What  is  the  guarantee   that  the private   developers  would  not  be  tempted  to  cut  a   lot  of  corners  in  order  to  make    hefty  profit  that  could  be  disastrous    in  long  run.  Institutions  like  the   Electricity  Department,  Ministry of  Water Resources  and   National  Planning  Commission  should  take  full   responsibility  to  guarantee  that  the  storage   dam  projects  have  been  planned,  constructed  and   operated  in  accordance  with   internationally   accepted  norms  and  practices. 

(Dr. Thapa writes on water resources)


Cover Story | CPN-UML Political Debate | Shyam Saran's DepartureInterview | Postal Services | Perspective
Domestic Child LaborersPlease Educate Us |
Human Rights | Editor's Note | The Bottom Line
News Notes | Briefs | Quote Unquote | Off The Record | Letters | Opinion
| Forum | Book Review


Send your feedback to the editor: spot@mail.com.np
2004   Mercantile Communications Pvt. Ltd. P.O. Box 876, Durbar Marg, Kathmandu, NEPAL. Tel : 977 1 4220 773, 4243 566 . Fax: 977 1 4225 407. Reproduction in any form is prohibited without prior permission. No part of the articles which appear in the internet version on SPOTLIGHT may be reproduced without the permission of Mercantile Communications Pvt. Ltd. For reprinting rights, please write to US. Send us your feedback: ABOUT US CONTACT US  HOME  
ADVERTISE WITH US

BACK TO THE TOP