![]() |
||
|
||
| OPINION |
NEPAL ELECTRICITY AUTHORITY:
Misleading Report By Dr. AB Thapa Very recently the Nepal
Electricity Authority (NEA) has published its annual report
2003/04 which has been presented in full
detail in newspapers such as The Kathmandu Post.
The report gives a very gloomy
picture of the NEA. It is stated in the
report that the NEA registered a net loss of
NRs. 1.78 billion despite the fact that the
electricity tariff of the NEA is one of the highest
in our region. Most of the NEA revenue
went towards payments to IPPs (private developers).
About 43 percent of the total revenue generated was
utilized in purchasing energy from IPPs
and about 30 percent to pay the HMGN in the form of
interest, principle and royalty. The cost of operation and
maintenance of the NEA operated power stations
is about 9 percent. The NEA is
perfectly right in pointing accusing finger at
the IPPs. But it would be wrong to
conclude that the burden of interest and
principles levied by the HMGN on external loans would have
even slightly contributed to worsening of the
NEAs financial situation. The fallacy of
the argument about the excessive burden of
the repayment to clear the HMGN loans is
revealed if the NEA report is slightly
scrutinized. In reality the present financial problems of the NEA are
mainly of its own making. The NEA was
warned of the dire consequences of careless
handling of the IPP projects a long time ago.
Water and Energy Commission had even circulated
a proposal suggesting an alternative plan that
would have been eight times cheaper by
comparison with the Khimti, Bhote-Kosi,
Indrawati type hydropower projects. A Big Confusion During the past financial year, according
to the reporting of the NEA, the electrical energy available for
use within the NEA system totaled 2381.496 GWh. This
comprised of 1345.654 GWh obtained from the NEAs own
hydropower plants with a total installed capacity
of 389 MW, and similarly 840.275 GWh purchased
from the IPPs owned hydropower plants with a total installed
capacity of about 141 MW. These data explain
that on an average the NEA owned hydropower
plants had been running for only 3460
hours in a year whereas the IPP hydropower
plants ran for 6000 hours. As a rule of thumb, the
hydropower plants with a small storage
reservoir to regulate the river flow on a daily basis
according to the need for water to meet the peak energy
demand are expected to run on an average
for about 5000 hours or slightly less in a year
unless the number of the average operating
hours in a year has to be decided from
some other specific considerations. In case of the
hydropower plants without a storage pond to regulate
river water on a daily basis, the installed capacity is decided
solely on the basis of the availability of guaranteed
river flow all the year round ( it is usually 90% probable
discharge) since such plants would not be able to operate
at higher capacity to meet the demand for peaking
energy that would have required water supplies to the turbines in excess
of the daily available guaranteed river water
flow. This scenario would certainly change and we
would have to adopt installed capacity in excess of
the firm capacity if we are in need for
seasonal energy. It is really frightening
to note that at present all IPP hydropower plants ( with the
exception of the Chilime Hydropower) without any storage
pond to regulate river water on a daily basis are perhaps
having installed capacity three times greater than
the firm capacity ( in case of Khimti Project the installed capacity is 60 MW
whereas the firm capacity is only 18 MW). As a result, they are
generating enormously large surplus seasonal energy , which
is totally wasted. A brief analysis of the NEA
report would raise fear in the mind
of all sensible people that the NEA
could soon become bankrupt if the present
laissez-faire hydropower development policy is
allowed to be continued The followings are some
of the main concerns. NEA Forced To Shut Down Its Power
Stations The NEA might be shutting
down partially or fully many of its own hydropower
plants for a considerable length of period
each year particularly in wet season to
receive electricity purchased from the IPP owned hydropower
plants. As a result, the NEA owned hydropower
plants are operating each year on an average less
than 3500 hours. Who Checks Electric Meters The yearly average
operating period of 6000 hours of the IPP
owned hydropower stations is somewhat too high
because the installed capacity of such hydropower plants is
several times greater than the firm capacity.
As mentioned earlier, the installed capacity of the
Khimti Project is 60 MW despite the fact that the
firm capacity is only 18 MW. It appears all the
more doubtful since some of the IPP owned
hydropower stations have to be completely shut
down for a long period each year to divert
water for irrigation. Moreover, during the wet
seasons the Bhote-Kosi, Indrawati and Khimti rivers would
be heavily laden with sediments. As a result, the
hydropower stations drawing water from those rivers
would have to be often shut down to flush out
the sediments that would, to a
considerable extent, curtail the electricity
generation. It would not be a great
surprise if the meters to register the supply
of electricity from the IPP hydropower stations might
not be in perfect order. Needless to say
that such meters should be periodically checked
and certified. Past experience has shown the
NEAs poor record of keeping the
instrumentation in good condition. When the
Kulekhani High Dam was on the verge of collapse
in 1980s due to geological problems, at
that time it was found that many of the
instruments set up during the construction period
to monitor the future movements of the
dam body were hardly functioning. A Scenario Without IPP Hydropower What would have happened now if
we did not have any of the IPP owned hydropower plants?
The NEA owned hydropower stations alone would have
generated about 1940 GWh per annum if it
is presumed that they operate 5000 hours each year.
Similarly the NEA owned thermal plants with a total
installed capacity of about 56 MW would have
generated about 150 GWh if it is presumed
that they would be operating on an average 3000
hours each year. If we would have purchased
about 300 GWh electricity( perhaps about 75 MW in capacity)
from India ( in the year 2002 it was 238 GWh ), the
total electricity available for use would have
been about 2390 GWh which is equal
to the availability of electricity for use last
year within the NEA system. Similarly the total
capacity in the system would have been about 520 MW against
the last years peak demand recorded at 515 MW. It
implies that the electricity procured from the
IPP owned hydropower stations is now almost
totally wasted. In other words we are
paying almost in vain Rs. 5.32 billion
(or 43% of the NEA revenue) to purchase
electricity from the IPP owned hydropower stations. Future Load Shedding The IPP owned hydropower plants
are not going to be helpful to the NEA in future also
to mitigate crisis of power shortage when the
demand for electricity further increases. The
total present firm capacity of all the
IPP owned hydropower stations might be only
about 60 MW during the critical dry
season months when the demand for electricity
is the highest despite the fact that the present
total installed capacity is about 140 MW. As a
result, the real total generating capacity in
the system would be only about 505 MW( excluding
procurement from India) which is less than the maximum
peak demand recorded at 515 MW last year. Thus
in the coming winter reason load shedding
would be inevitable if electricity is not imported
from India. Can We Export Seasonal Energy? It is quite unfortunate that some of
our friends in the Government are placing high hopes
on export of seasonal energy to India to promote
IPP projects. We should beware of such misleading
perception. Our own study of the Upper Karnali Project
carried out with the assistance of the World
Bank explains that the value of our seasonal
energy to Indian system to displace temporarily
fossil fuel could be only about 10% of the
value of the firm energy whereas the cost
of energy transmission to India ( wheeling charge)
could be somewhere around 15% of the total value
of the mostly firm energy based on the
recent agreements reached between various states
of India. Thus we would be incurring a loss by
exporting seasonal energy if special circumstances
did not warrant India to buy such energy at a
fairly high price. Have We Engineers No Shame? Very recently the NEA is about
to take a fatal decision on the 300 MW Upper
Karnali Project that would be extremely harmful to our nation
and it would also be a big shame on all
Nepalese engineering community. We, in engineering
profession, would be seen to have misled the
country to take such decision by holding back
the true findings of the 300 MW Upper Karnali Project
study carried out under the aegis of the World Bank that
warns us of the dire consequences if this project is
implemented. Nepal is now facing
problems of convincing the international donor
community to lend annually about US $ 500
million in the years ahead to launch
development works for poverty reduction. It would
certainly surprise us to learn that the 4,000 MW Upper
Karnali Storage Project alone could provide Nepal
annually about US $ 400 million in royalty to
our country immediately after the completion of
the project construction, despite the fact that
this project is far smaller than the
Karnali Chisapani Project. It can easily be
seen that the Upper Karnali Storage Project is
certainly the best among the projects identified
so far in Nepal for the generation of
cheap peaking power. The Nepal Electricity
Authority is soon going to decide to
implement the 300 MW Mini Upper Karnali Project
that would displace the 4,000 MW Upper Karnali
Storage Project. ( Please read the article NEA Killing Goose Laying
Golden Eggs - SPOTLIGHT May 21, 2004) The 4,000 MW Upper
Karnali Storage Project and the small 300 MW Mini
Upper Karnali Project yielding very limited
benefits are mutually exclusive. Thus, the Nepal
Electricity Authority is about to kill the
goose that lays the golden eggs. However, it
is hoped that the NEA would carefully go
through the Upper Karnali Project study report and
refrain from taking the disastrous decision to implement
the small 300 MW Upper Karnali Project that would also
have portrayed all of us as utter fools in
the eyes of foreigners. (Dr. Thapa writes on water resources) |
Send your feedback to the
editor: spot@mail.com.np |