![]() |
||
|
||
| OPINION |
Load-Shedding And NEA's Misplaced Confidence By Dr. AB Thapa Just a month back the NEA was claiming that
it has in its system about 100 MW surplus power to be exported to India but
now it is announcing that it became necessary to resort to load-shedding for about 2
hours in the evening peak demand time affecting all its consumers once
in a week. It shows that the NEA supply of
electricity would thus be reduced by about 70
MW. According to the NEA reporting the malfunctioning of one of the
units of the Kali-Gandaki Hydropower Station that led to 48 MW
shortfall in total availability of power in the NEA
system is the cause of the present load-shedding. Everybody would
be astonished to learn of such quite conflicting news.
They would be eager to be informed about the true
cause of the power supply crisis. Why the NEA is
compelled to face the fact that there is already a shortfall of
about 20 MW in the NEA system despite the NEAs very recent
claim to large exportable surplus estimated at around 100 MW? The NEA Annual Report Very recently the Nepal
Electricity Authority (NEA) has published its annual report
2003/04 which has been presented in full
detail in newspapers such as The Kathmandu Post.
The report gives a very gloomy
picture of the NEA. It is stated in the
report that the NEA registered a net loss of
NRs. 1.78 billion despite the fact that the
electricity tariff of the NEA is one of the highest
in our region. Most of the NEA revenue
went towards payments to IPPs (private developers).
About 43 percent of the total revenue generated was
utilized in purchasing energy from IPPs
and about 30 percent to HMGN in the form of interest,
principle and royalty. The cost of operation and
maintenance of the NEA operated power stations
is about 9 percent. The NEA is
perfectly right in pointing accusing finger at
the IPPs. But it would be wrong to
conclude that the burden of interest and
principles levied by the HMGN on external loans would have
even slightly contributed to worsening of the
NEAs financial situation. The fallacy of
the argument about the excessive burden of
the repayment to clear the HMGN loans is
revealed if the NEA report is slightly
scrutinized. In reality the present financial problems of the NEA are
mainly of its own making. The NEA was
warned of the dire consequences of careless
handling of the IPP projects a long time ago.
Water and Energy Commission had even circulated
a proposal suggesting an alternative plan that
would have been eight times cheaper by
comparison with the Khimti, Bhote-Kosi,
Indrawati type hydropower projects. NEA Forced To Shut Down Its Power
Stations The NEA might be shutting
down partially or fully many of its own hydropower
plants for a considerable length of period
each year particularly in wet season to
receive electricity purchased from the IPP owned hydropower
plants. As a result, the NEA owned hydropower
plants are operating each year on an average less
than 3500 hours whereas the IPP owned hydropower plants are reported to
be operating 6000 hours. During the past financial year, according
to the reporting of the NEA, the electrical energy available for
use within the NEA system totaled 2381.496 GWh. This
comprised of 1345.654 GWh obtained from the NEAs own
hydropower plants with a total installed capacity
of 389 MW, and similarly 840.275 GWh purchased
from the IPPs owned hydropower plants with a total installed
capacity of about 141 MW. These data explain
that on an average the NEA owned hydropower
plants had been running for only 3460
hours in a year whereas the IPP hydropower
plants 6000 hours. As a rule of thumb, the hydropower
plants with a small storage reservoir to
regulate the river flow on a daily basis according to the need for
water to meet the peak energy demand are expected
to run on an average for about 5000 hours or
slightly less in a year unless the number of
the average operating hours in a year has to
be decided from some other specific
considerations. In case of the hydropower plants without
a storage pond to regulate river water on a daily basis, the
installed capacity is decided solely on the basis of the
availability of guaranteed river flow all the year round (
it is usually 90% probable discharge) since such plants would not
be able to operate at higher capacity to meet
the demand for peaking energy that would have required water
supplies to the turbines in excess of the daily available
guaranteed river water flow. This scenario would certainly
change and we would have to adopt installed
capacity in excess of the firm capacity if we are in
need for seasonal energy. IPP Supplied Electricity Totally
Wasted What would have happened now if
we did not have any of the IPP owned hydropower plants?
The NEA owned hydropower stations alone would have
generated about 1940 GWh per annum if it
is presumed that they operate 5000 hours each year.
Similarly the NEA owned thermal plants with a total
installed capacity of about 56 MW would have
generated about 150 GWh if it is presumed
that they would be operating on an average 3000
hours each year. If we would have purchased
about 300 GWh electricity( perhaps about 75 MW in capacity)
from India ( in the year 2002 it was 238 GWh ), the
total electricity available for use would have
been about 2390 GWh which is equal
to the availability of electricity for use last
year within the NEA system. Similarly the total
capacity in the system would have been about 520 MW against
the last years peak demand recorded at 515 MW. It
implies that the electricity procured from the
IPP owned hydropower stations is now almost
totally wasted. In other words we are
paying almost in vain Rs. 5.32 billion (
or 43% of the NEA revenue) to purchase
electricity from the IPP owned hydropower stations. The NEA Could Soon Become Bankrupt It is really frightening
to note that at present all IPP hydropower plants ( with the
exception of the Chilime Hydropower) without any storage
pond to regulate river water on a daily basis are perhaps
having installed capacity three times greater than
the firm capacity ( in case of Khimti Project the installed capacity is 60 MW
whereas the firm capacity is only 18 MW). As a result, they are
generating enormously large surplus seasonal energy , which
is totally wasted. A brief analysis of the NEA
report would raise fear in the mind
of all sensible people that the NEA
could soon become bankrupt if the present
laissez-faire hydropower development policy is
allowed to be continued The followings are few
other concerns. . Who Checks Electric Meters The yearly average
operating period of 6000 hours of the IPP
owned hydropower stations is somewhat too high
because the installed capacity of such hydropower plants is
several times greater than the firm capacity.
As mentioned earlier, the installed capacity of the
Khimti Project is 60 MW despite the fact that the
firm capacity is only 18 MW. It appears all the
more doubtful since some of the IPP owned
hydropower stations have to be completely shut
down for a long period each year to divert
water for irrigation. Moreover, during the wet
seasons the Bhote-Kosi, Indrawati and Khimti rivers would
be heavily laden with sediments. As a result, the
hydropower stations drawing water from those rivers
would have to be too often shut down to flush
out the sediments that would to a
considerable extent curtail the electricity
generation. It would not be a great
surprise if the meters to register the supply
of electricity from the IPP hydropower stations might
not be in perfect order. Needless to say
that such meters should be periodically checked
and certified. Past experience has shown the
NEAs poor record of keeping the
instrumentation in good condition. When the
Kulekhani High Dam was on the verge of collapse
in 1980s due to geological problems, at
that time it was found that many of the
instruments set up during the construction period
to monitor the future movements of the
dam body were hardly functioning. Future Load Shedding The IPP owned hydropower plants
are not going to be helpful to the NEA in future also
to mitigate crisis of power shortage when the
demand for electricity further increases. The
total present firm capacity of all the
IPP owned hydropower stations might be only
about 60 MW during the critical dry
season months when the demand for electricity
is the highest despite the fact that the present
total installed capacity is about 140 MW. As a
result, the real total generating capacity in
the system would be only about 505 MW( excluding
procurement from India) which is less than the maximum
peak demand recorded at 515 MW last year. Thus
in the coming winter reason load shedding
would be inevitable if electricity is not imported
from India. Can We Export Seasonal Energy? It is quite unfortunate that some of
our friends in the Government are placing high hopes
on export of seasonal energy to India to promote
IPP projects. We should beware of such misleading
perception. Our own study of the Upper Karnali
Project carried out with the assistance of the
World Bank explains that the value of our
seasonal energy to Indian system to displace
temporarily fossil fuel could be only about 10% of
the value of the firm energy whereas the
cost of energy transmission to India ( wheeling charge)
could be somewhere around 15% of the total value
of the mostly firm energy based on the
recent agreements reached between various states
of India. Thus we would be incurring a loss by
exporting seasonal energy if special circumstances
did not warrant India to buy such energy at a
fairly high price. In Conclusion It is often said
that many developing countries are unable to
bolster up the economy at a
reasonable pace not for want of natural
resources or capital. They are progressing
very slowly because their policy makers and
planners posses neither a clear vision
of their countrys development perspectives nor
the ability and true dedication to lead the
country in the path to victory over
underdevelopment and backwardness. Certainly in
this matter Nepal is not an exception. Our
country is also suffering from the same
type of ailment. Planners and policy makers
in our country need to have clear vision
and true dedication to their works. At present Nepal Electricity Authority is
facing a terrible financial crisis. The NEA had to resort to repeated
hiking of the electricity tariff to cover its losses.
Unfortunately nobody is seen to be truly interested
to diagnosis the ailment of the NEA. It is hoped
that the PDF loan going to be provided to Nepal by the World Bank
would not be spent to further worsen the financial situation of the
NEA by investing on projects like the Khimti, Bhote-Kosi, Indrawati. (Dr. Thapa writes on water resources) |
|| Cover
Story || Earthquake Day || Politics || Vat Hike || Interview || Ldta || |
Send your feedback to the
editor: spot@mail.com.np |